Updating the database of the Illinois Compiled Statutes (ILCS) is an ongoing process.
Recent laws may not yet be included in the ILCS database, but they are found on this site as
Public
Acts soon after they become law. For information concerning the relationship between statutes and Public Acts, refer to the
Guide.
Because the statute database is maintained primarily for legislative drafting purposes,
statutory changes are sometimes included in the statute database before they take effect.
If the source note at the end of a Section of the statutes includes a Public Act that has
not yet taken effect, the version of the law that is currently in effect may have already
been removed from the database and you should refer to that Public Act to see the changes
made to the current law.
(415 ILCS 5/58.16)
Sec. 58.16. Construction of school; requirements. This Section applies
only to counties with a population of more than 3,000,000. In this Section,
"school" means any public school located in whole or in part in a county with
a population of more than 3,000,000. No person shall commence construction on
real property of a building intended for use as a school unless:
(1) a Phase I Environmental Audit, conducted in |
| accordance with Section 22.2 of this Act, is obtained;
|
|
(2) if the Phase I Environmental Audit discloses the
|
| presence or likely presence of a release or a substantial threat of a release of a regulated substance at, on, to, or from the real property, a Phase II Environmental Audit, conducted in accordance with Section 22.2 of this Act, is obtained; and
|
|
(3) if the Phase II Environmental Audit discloses the
|
| presence or likely presence of a release or a substantial threat of a release of a regulated substance at, on, to, or from the real property: (i) the real property is enrolled in the Site Remediation Program, and (ii) the remedial action plan is approved by the Agency, if a remedial action plan is required by Board regulations.
|
|
No person shall cause or allow any person to occupy a building intended
to be used as a school for which a remedial action plan is required by Board
regulations unless all work pursuant to the remedial action plan is completed.