(815 ILCS 603/1)
Sec. 1. Short title. This Act may be cited as the Contractor Prompt Payment Act.
(Source: P.A. 95-567, eff. 8-31-07.) |
(815 ILCS 603/5)
Sec. 5. Definitions. In this Act: (a) "Payment application" means, in accordance with the terms and definitions of
the applicable contract, any invoice, bill or other request for periodic payment, final payment, payment of change order or request for release of retainage from the contractor to the owner. (b) "Construction contract" means a contract or subcontract, entered into after the effective date of this Act, for the design, construction, alteration, improvement, or repair of Illinois real property, except for contracts that require the expenditure of public funds and contracts for the design, construction, alteration, improvement, or repair of single family residences or multiple family residences with 12 or fewer units in a single building. (c) "Contractor" and "subcontractor" shall have the meanings ascribed to them by the Illinois Mechanics Lien Act and cases decided under that Act.
(Source: P.A. 95-567, eff. 8-31-07.) |
(815 ILCS 603/10)
Sec. 10. Construction contracts. All construction contracts shall be deemed to provide the following: (1) If a contractor has performed in accordance with | ||
| ||
(2) If a subcontractor has performed in accordance | ||
| ||
(Source: P.A. 100-201, eff. 8-18-17.) |
(815 ILCS 603/15)
Sec. 15. Interest; suspension of performance. (a) If a payment due pursuant to the provisions of this Act is not made in a timely manner, the delinquent party shall be liable for the amount of that payment, plus interest at a rate equal to 10% per annum. (b) A contractor or subcontractor who is not paid as required by this Act may, after providing 7 calendar days' written notice to the party failing to make the required payment, suspend performance of a construction contract without penalty for breach of contract, until the payment required pursuant to this Act is made. (c) The interest imposed by this Act shall not be duplicative of the interest charged under the Mechanics Lien Act.
(Source: P.A. 95-567, eff. 8-31-07.) |
(815 ILCS 603/20) Sec. 20. Retainage. No construction contract may permit the withholding of retainage from any payment in excess of the amounts permitted in this Section. A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.
(Source: P.A. 101-432, eff. 8-20-19.) |
(815 ILCS 603/99)
Sec. 99. Effective date. This Act shall take effect upon becoming law.
(Source: P.A. 95-567, eff. 8-31-07.) |