 1        AN  ACT  to  amend  the  Public Utilities Act by changing
 2    Section 8-501.

 3        Be it enacted by the People of  the  State  of  Illinois,
 4    represented in the General Assembly:

 5        Section  5.   The  Public  Utilities  Act  is  amended by
 6    changing Section 8-501 as follows:

 7        (220 ILCS 5/8-501) (from Ch. 111 2/3, par. 8-501)
 8        Sec.  8-501.  Intrastate  gas  pipelines;  extension  and
 9    interconnection. Whenever the Commission, after a hearing had
10    upon its own motion or upon complaint, shall  find  that  the
11    rules,   regulations,   practices,   equipment,   appliances,
12    facilities  or  service of any public utility, or the methods
13    of manufacture, distribution, transmission, storage or supply
14    employed by it, are unjust, unreasonable,  unsafe,  improper,
15    inadequate  or  insufficient,  the Commission shall determine
16    the just, reasonable, safe, proper,  adequate  or  sufficient
17    rules,   regulations,   practices,   equipment,   appliances,
18    facilities,  service  or  methods  to be observed, furnished,
19    constructed, enforced or employed and it shall fix  the  same
20    by  its  order,  decision, rule or regulation. The Commission
21    shall prescribe rules and regulations for the performance  of
22    any  service  or  the  furnishing  of  any  commodity  of the
23    character furnished or supplied by any public utility.
24        Whenever the Commission shall determine, after a hearing,
25    that the  public  convenience  and  necessity  requires  that
26    interconnection  or  extension of intrastate gas distribution
27    or transmission  pipelines  or  facilities  is  necessary  to
28    insure that natural gas service is made available to Illinois
29    natural gas customers at rates which are just and reasonable,
30    the   Commission   shall  determine  the  interconnection  or
31    extension of pipelines or facilities which  is  necessary  to
 
                            -2-                LRB9101403JScs
 1    provide such service and shall direct that such facilities be
 2    established,  according  to a schedule set by the Commission.
 3    The  Commission  shall  direct  that  any  utility  supplying
 4    natural  gas  for  such  interconnection  or   extension   of
 5    intrastate  gas  distribution  or  transmission  pipelines or
 6    facilities shall recover all costs and charges related to the
 7    interconnection or extension from the utility receiving  such
 8    gas  at  no  increased  cost  to the customers of any utility
 9    supplying the gas. The Commission is directed  to  report  to
10    the  General  Assembly  by  September 20, 1984, detailing its
11    findings and the steps which it has taken to provide for such
12    intrastate interconnections or extensions.
13    (Source: P.A. 84-617.)