Public Act 102-0771 | ||||
| ||||
| ||||
AN ACT concerning health.
| ||||
Be it enacted by the People of the State of Illinois,
| ||||
represented in the General Assembly:
| ||||
Section 5. The Lead Poisoning Prevention Act is amended by | ||||
changing Section 9 as follows:
| ||||
(410 ILCS 45/9) (from Ch. 111 1/2, par. 1309)
| ||||
Sec. 9. Procedures upon determination of lead hazard.
| ||||
(1) If the inspection report identifies a lead hazard, the | ||||
Department or
delegate agency shall serve a mitigation notice | ||||
on the property owner that the
owner is required to mitigate | ||||
the lead hazard, and shall indicate the time
period specified | ||||
in this Section in which the owner must complete the
| ||||
mitigation. The notice shall include information describing | ||||
mitigation
activities which meet the requirements of this Act.
| ||||
(2) If the inspection report identifies a lead hazard, the | ||||
owner shall
mitigate the lead hazard in a manner prescribed by | ||||
the Department and within
the time limit prescribed by this | ||||
Section. The Department shall adopt rules
regarding acceptable | ||||
methods of mitigating a lead hazard. If the source of the
lead | ||||
hazard identified in the inspection report is lead paint or | ||||
any other lead-bearing
surface coating, the lead hazard shall | ||||
be deemed to have been mitigated
if:
| ||||
(A) the surface identified as the source of the lead |
hazard is no longer in
a condition that produces a | ||
hazardous level of lead chips, flakes, dust
or any other | ||
form of lead-bearing substance, that can be ingested or | ||
inhaled by
humans;
| ||
(B) the surface identified as the source of the lead | ||
hazard is no longer accessible
to children and could not | ||
reasonably be chewed on by children; or | ||
(C) the surface coating identified as the source of | ||
the lead hazard is either removed
or covered, or child | ||
access to the lead-bearing surface is otherwise prevented | ||
as
prescribed by the Department.
| ||
(3) Mitigation activities which involve the destruction or | ||
disturbance of
any lead-bearing surface shall be conducted by | ||
a licensed lead abatement contractor
using licensed lead | ||
abatement supervisors or lead abatement workers. The | ||
Department may prescribe by rule
mitigation activities that | ||
may be performed without a licensed lead abatement contractor, | ||
lead abatement supervisor, or lead abatement
worker. The | ||
Department may, on a case by case basis, grant a waiver of the
| ||
requirement to use licensed lead abatement contractors, lead | ||
abatement supervisors, and lead abatement workers, provided
| ||
the waiver does not endanger the health or safety of humans.
| ||
(4) The Department shall establish procedures whereby an | ||
owner,
after receiving a mitigation notice under this Section, | ||
may submit a
mitigation plan to the Department or delegate | ||
agency for review and approval.
|
(5) When a mitigation notice is issued for a dwelling unit | ||
inspected as a
result of an elevated blood lead level in a | ||
pregnant person or a child, or if
the dwelling unit is occupied | ||
by a child 6 years of age or younger or a pregnant person, the | ||
owner shall mitigate the hazard within 30 days of receiving | ||
the
notice; when no such child or pregnant person occupies the | ||
dwelling unit, the owner shall complete the mitigation within | ||
90 days.
| ||
(6) An owner may apply to the Department or its delegate | ||
agency
for an extension of the deadline for mitigation. If the | ||
Department or its
delegate agency determines that the owner is | ||
making substantial progress
toward mitigation, or that the | ||
failure to meet the deadline is the result
of a shortage of | ||
licensed lead abatement contractors, lead abatement | ||
supervisors, or lead abatement workers, or that the
failure to | ||
meet the deadline is because the owner is awaiting the review
| ||
and approval of a mitigation plan, the Department or delegate | ||
agency may
grant an extension of the deadline.
| ||
(7) The Department or its delegate agency shall may , after | ||
the deadline set for
completion of mitigation, conduct a | ||
follow-up inspection of any dwelling unit for
which a | ||
mitigation notice was issued for the purpose of determining | ||
whether the
mitigation actions required have been completed | ||
and whether the activities have
sufficiently mitigated the | ||
lead hazard as provided under this Section. The
Department or | ||
its delegate agency may conduct a follow-up inspection upon |
the
request of an owner or resident. If, upon completing the | ||
follow-up inspection,
the Department or its delegate agency | ||
finds that the lead hazard for which the
mitigation notice was | ||
issued is not mitigated, the Department or its delegate
agency | ||
shall serve the owner with notice of the deficiency and a | ||
mitigation
order. The order shall indicate the specific | ||
actions the owner must
take to comply with the mitigation | ||
requirements of this Act, which may
include lead abatement if | ||
lead abatement is the sole means by which the lead hazard
can | ||
be mitigated. The order shall also include the date by which | ||
the
mitigation shall be completed. If, upon completing the | ||
follow-up
inspection, the Department or delegate agency finds | ||
that the mitigation
requirements of this Act have been | ||
satisfied, the Department or delegate
agency shall provide the | ||
owner with a certificate of compliance stating
that the | ||
required mitigation has been accomplished.
| ||
(Source: P.A. 98-690, eff. 1-1-15 .)
|