|
Public Act 103-0613 |
HB5539 Enrolled | LRB103 38494 CES 68630 b |
|
|
AN ACT concerning utilities. |
Be it enacted by the People of the State of Illinois, |
represented in the General Assembly: |
Section 5. The Public Utilities Act is amended by changing |
Sections 8-103, 8-103B, and 8-104 as follows: |
(220 ILCS 5/8-103) |
Sec. 8-103. Energy efficiency and demand-response |
measures. |
(a) It is the policy of the State that electric utilities |
are required to use cost-effective energy efficiency and |
demand-response measures to reduce delivery load. Requiring |
investment in cost-effective energy efficiency and |
demand-response measures will reduce direct and indirect costs |
to consumers by decreasing environmental impacts and by |
avoiding or delaying the need for new generation, |
transmission, and distribution infrastructure. It serves the |
public interest to allow electric utilities to recover costs |
for reasonably and prudently incurred expenses for energy |
efficiency and demand-response measures. As used in this |
Section, "cost-effective" means that the measures satisfy the |
total resource cost test. The low-income measures described in |
subsection (f)(4) of this Section shall not be required to |
meet the total resource cost test. For purposes of this |
|
Section, the terms "energy-efficiency", "demand-response", |
"electric utility", and "total resource cost test" shall have |
the meanings set forth in the Illinois Power Agency Act. For |
purposes of this Section, the amount per kilowatthour means |
the total amount paid for electric service expressed on a per |
kilowatthour basis. For purposes of this Section, the total |
amount paid for electric service includes without limitation |
estimated amounts paid for supply, transmission, distribution, |
surcharges, and add-on-taxes. |
(a-5) This Section applies to electric utilities serving |
500,000 or less but more than 200,000 retail customers in this |
State. Through December 31, 2017, this Section also applies to |
electric utilities serving more than 500,000 retail customers |
in the State. |
(b) Electric utilities shall implement cost-effective |
energy efficiency measures to meet the following incremental |
annual energy savings goals: |
(1) 0.2% of energy delivered in the year commencing |
June 1, 2008; |
(2) 0.4% of energy delivered in the year commencing |
June 1, 2009; |
(3) 0.6% of energy delivered in the year commencing |
June 1, 2010; |
(4) 0.8% of energy delivered in the year commencing |
June 1, 2011; |
(5) 1% of energy delivered in the year commencing June |
|
1, 2012; |
(6) 1.4% of energy delivered in the year commencing |
June 1, 2013; |
(7) 1.8% of energy delivered in the year commencing |
June 1, 2014; and |
(8) 2% of energy delivered in the year commencing June |
1, 2015 and each year thereafter. |
Electric utilities may comply with this subsection (b) by |
meeting the annual incremental savings goal in the applicable |
year or by showing that the total cumulative annual savings |
within a 3-year planning period associated with measures |
implemented after May 31, 2014 was equal to the sum of each |
annual incremental savings requirement from May 31, 2014 |
through the end of the applicable year. |
(c) Electric utilities shall implement cost-effective |
demand-response measures to reduce peak demand by 0.1% over |
the prior year for eligible retail customers, as defined in |
Section 16-111.5 of this Act, and for customers that elect |
hourly service from the utility pursuant to Section 16-107 of |
this Act, provided those customers have not been declared |
competitive. This requirement commences June 1, 2008 and |
continues for 10 years. |
(d) Notwithstanding the requirements of subsections (b) |
and (c) of this Section, an electric utility shall reduce the |
amount of energy efficiency and demand-response measures |
implemented over a 3-year planning period by an amount |
|
necessary to limit the estimated average annual increase in |
the amounts paid by retail customers in connection with |
electric service due to the cost of those measures to: |
(1) in 2008, no more than 0.5% of the amount paid per |
kilowatthour by those customers during the year ending May |
31, 2007; |
(2) in 2009, the greater of an additional 0.5% of the |
amount paid per kilowatthour by those customers during the |
year ending May 31, 2008 or 1% of the amount paid per |
kilowatthour by those customers during the year ending May |
31, 2007; |
(3) in 2010, the greater of an additional 0.5% of the |
amount paid per kilowatthour by those customers during the |
year ending May 31, 2009 or 1.5% of the amount paid per |
kilowatthour by those customers during the year ending May |
31, 2007; |
(4) in 2011, the greater of an additional 0.5% of the |
amount paid per kilowatthour by those customers during the |
year ending May 31, 2010 or 2% of the amount paid per |
kilowatthour by those customers during the year ending May |
31, 2007; and |
(5) thereafter, the amount of energy efficiency and |
demand-response measures implemented for any single year |
shall be reduced by an amount necessary to limit the |
estimated average net increase due to the cost of these |
measures included in the amounts paid by eligible retail |
|
customers in connection with electric service to no more |
than the greater of 2.015% of the amount paid per |
kilowatthour by those customers during the year ending May |
31, 2007 or the incremental amount per kilowatthour paid |
for these measures in 2011. |
No later than June 30, 2011, the Commission shall review |
the limitation on the amount of energy efficiency and |
demand-response measures implemented pursuant to this Section |
and report to the General Assembly its findings as to whether |
that limitation unduly constrains the procurement of energy |
efficiency and demand-response measures. |
(e) Electric utilities shall be responsible for overseeing |
the design, development, and filing of energy efficiency and |
demand-response plans with the Commission. Electric utilities |
shall implement 100% of the demand-response measures in the |
plans. Electric utilities shall implement 75% of the energy |
efficiency measures approved by the Commission, and may, as |
part of that implementation, outsource various aspects of |
program development and implementation. The remaining 25% of |
those energy efficiency measures approved by the Commission |
shall be implemented by the Department of Commerce and |
Economic Opportunity, and must be designed in conjunction with |
the utility and the filing process. The Department may |
outsource development and implementation of energy efficiency |
measures. A minimum of 10% of the entire portfolio of |
cost-effective energy efficiency measures shall be procured |
|
from units of local government, municipal corporations, school |
districts, public institutions of higher education, and |
community college districts. The Department shall coordinate |
the implementation of these measures. |
The apportionment of the dollars to cover the costs to |
implement the Department's share of the portfolio of energy |
efficiency measures shall be made to the Department once the |
Department has executed rebate agreements, grants, or |
contracts for energy efficiency measures and provided |
supporting documentation for those rebate agreements, grants, |
and contracts to the utility. The Department is authorized to |
adopt any rules necessary and prescribe procedures in order to |
ensure compliance by applicants in carrying out the purposes |
of rebate agreements for energy efficiency measures |
implemented by the Department made under this Section. |
The details of the measures implemented by the Department |
shall be submitted by the Department to the Commission in |
connection with the utility's filing regarding the energy |
efficiency and demand-response measures that the utility |
implements. |
A utility providing approved energy efficiency and |
demand-response measures in the State shall be permitted to |
recover costs of those measures through an automatic |
adjustment clause tariff filed with and approved by the |
Commission. The tariff shall be established outside the |
context of a general rate case. Each year the Commission shall |
|
initiate a review to reconcile any amounts collected with the |
actual costs and to determine the required adjustment to the |
annual tariff factor to match annual expenditures. |
Each utility shall include, in its recovery of costs, the |
costs estimated for both the utility's and the Department's |
implementation of energy efficiency and demand-response |
measures. Costs collected by the utility for measures |
implemented by the Department shall be submitted to the |
Department pursuant to Section 605-323 of the Civil |
Administrative Code of Illinois, shall be deposited into the |
Energy Efficiency Portfolio Standards Fund, and shall be used |
by the Department solely for the purpose of implementing these |
measures. A utility shall not be required to advance any |
moneys to the Department but only to forward such funds as it |
has collected. The Department shall report to the Commission |
on an annual basis regarding the costs actually incurred by |
the Department in the implementation of the measures. Any |
changes to the costs of energy efficiency measures as a result |
of plan modifications shall be appropriately reflected in |
amounts recovered by the utility and turned over to the |
Department. |
The portfolio of measures, administered by both the |
utilities and the Department, shall, in combination, be |
designed to achieve the annual savings targets described in |
subsections (b) and (c) of this Section, as modified by |
subsection (d) of this Section. |
|
The utility and the Department shall agree upon a |
reasonable portfolio of measures and determine the measurable |
corresponding percentage of the savings goals associated with |
measures implemented by the utility or Department. |
No utility shall be assessed a penalty under subsection |
(f) of this Section for failure to make a timely filing if that |
failure is the result of a lack of agreement with the |
Department with respect to the allocation of responsibilities |
or related costs or target assignments. In that case, the |
Department and the utility shall file their respective plans |
with the Commission and the Commission shall determine an |
appropriate division of measures and programs that meets the |
requirements of this Section. |
If the Department is unable to meet incremental annual |
performance goals for the portion of the portfolio implemented |
by the Department, then the utility and the Department shall |
jointly submit a modified filing to the Commission explaining |
the performance shortfall and recommending an appropriate |
course going forward, including any program modifications that |
may be appropriate in light of the evaluations conducted under |
item (7) of subsection (f) of this Section. In this case, the |
utility obligation to collect the Department's costs and turn |
over those funds to the Department under this subsection (e) |
shall continue only if the Commission approves the |
modifications to the plan proposed by the Department. |
(f) No later than November 15, 2007, each electric utility |
|
shall file an energy efficiency and demand-response plan with |
the Commission to meet the energy efficiency and |
demand-response standards for 2008 through 2010. No later than |
October 1, 2010, each electric utility shall file an energy |
efficiency and demand-response plan with the Commission to |
meet the energy efficiency and demand-response standards for |
2011 through 2013. Every 3 years thereafter, each electric |
utility shall file, no later than September 1, an energy |
efficiency and demand-response plan with the Commission. If a |
utility does not file such a plan by September 1 of an |
applicable year, it shall face a penalty of $100,000 per day |
until the plan is filed. Each utility's plan shall set forth |
the utility's proposals to meet the utility's portion of the |
energy efficiency standards identified in subsection (b) and |
the demand-response standards identified in subsection (c) of |
this Section as modified by subsections (d) and (e), taking |
into account the unique circumstances of the utility's service |
territory. The Commission shall seek public comment on the |
utility's plan and shall issue an order approving or |
disapproving each plan within 5 months after its submission. |
If the Commission disapproves a plan, the Commission shall, |
within 30 days, describe in detail the reasons for the |
disapproval and describe a path by which the utility may file a |
revised draft of the plan to address the Commission's concerns |
satisfactorily. If the utility does not refile with the |
Commission within 60 days, the utility shall be subject to |
|
penalties at a rate of $100,000 per day until the plan is |
filed. This process shall continue, and penalties shall |
accrue, until the utility has successfully filed a portfolio |
of energy efficiency and demand-response measures. Penalties |
shall be deposited into the Energy Efficiency Trust Fund. In |
submitting proposed energy efficiency and demand-response |
plans and funding levels to meet the savings goals adopted by |
this Act the utility shall: |
(1) Demonstrate that its proposed energy efficiency |
and demand-response measures will achieve the requirements |
that are identified in subsections (b) and (c) of this |
Section, as modified by subsections (d) and (e). |
(2) Present specific proposals to implement new |
building and appliance standards that have been placed |
into effect. |
(3) Present estimates of the total amount paid for |
electric service expressed on a per kilowatthour basis |
associated with the proposed portfolio of measures |
designed to meet the requirements that are identified in |
subsections (b) and (c) of this Section, as modified by |
subsections (d) and (e). |
(4) Coordinate with the Department to present a |
portfolio of energy efficiency measures proportionate to |
the share of total annual utility revenues in Illinois |
from households at or below 150% of the poverty level. The |
energy efficiency programs shall be targeted to households |
|
with incomes at or below 80% of area median income. |
(5) Demonstrate that its overall portfolio of energy |
efficiency and demand-response measures, not including |
programs covered by item (4) of this subsection (f), are |
cost-effective using the total resource cost test and |
represent a diverse cross-section of opportunities for |
customers of all rate classes to participate in the |
programs. |
(6) Include a proposed cost-recovery tariff mechanism |
to fund the proposed energy efficiency and demand-response |
measures and to ensure the recovery of the prudently and |
reasonably incurred costs of Commission-approved programs. |
(7) Provide for an annual independent evaluation of |
the performance of the cost-effectiveness of the utility's |
portfolio of measures and the Department's portfolio of |
measures, as well as a full review of the 3-year results of |
the broader net program impacts and, to the extent |
practical, for adjustment of the measures on a |
going-forward basis as a result of the evaluations. The |
resources dedicated to evaluation shall not exceed 3% of |
portfolio resources in any given year. |
(g) No more than 3% of energy efficiency and |
demand-response program revenue may be allocated for |
demonstration of breakthrough equipment and devices. |
(h) This Section does not apply to an electric utility |
that on December 31, 2005 provided electric service to fewer |
|
than 100,000 customers in Illinois. |
(i) If, after 2 years, an electric utility fails to meet |
the efficiency standard specified in subsection (b) of this |
Section, as modified by subsections (d) and (e), it shall make |
a contribution to the Low-Income Home Energy Assistance |
Program. The combined total liability for failure to meet the |
goal shall be $1,000,000, which shall be assessed as follows: |
a large electric utility shall pay $665,000, and a medium |
electric utility shall pay $335,000. If, after 3 years, an |
electric utility fails to meet the efficiency standard |
specified in subsection (b) of this Section, as modified by |
subsections (d) and (e), it shall make a contribution to the |
Low-Income Home Energy Assistance Program. The combined total |
liability for failure to meet the goal shall be $1,000,000, |
which shall be assessed as follows: a large electric utility |
shall pay $665,000, and a medium electric utility shall pay |
$335,000. In addition, the responsibility for implementing the |
energy efficiency measures of the utility making the payment |
shall be transferred to the Illinois Power Agency if, after 3 |
years, or in any subsequent 3-year period, the utility fails |
to meet the efficiency standard specified in subsection (b) of |
this Section, as modified by subsections (d) and (e). The |
Agency shall implement a competitive procurement program to |
procure resources necessary to meet the standards specified in |
this Section as modified by subsections (d) and (e), with |
costs for those resources to be recovered in the same manner as |
|
products purchased through the procurement plan as provided in |
Section 16-111.5. The Director shall implement this |
requirement in connection with the procurement plan as |
provided in Section 16-111.5. |
For purposes of this Section, (i) a "large electric |
utility" is an electric utility that, on December 31, 2005, |
served more than 2,000,000 electric customers in Illinois; |
(ii) a "medium electric utility" is an electric utility that, |
on December 31, 2005, served 2,000,000 or fewer but more than |
100,000 electric customers in Illinois; and (iii) Illinois |
electric utilities that are affiliated by virtue of a common |
parent company are considered a single electric utility. |
(j) If, after 3 years, or any subsequent 3-year period, |
the Department fails to implement the Department's share of |
energy efficiency measures required by the standards in |
subsection (b), then the Illinois Power Agency may assume |
responsibility for and control of the Department's share of |
the required energy efficiency measures. The Agency shall |
implement a competitive procurement program to procure |
resources necessary to meet the standards specified in this |
Section, with the costs of these resources to be recovered in |
the same manner as provided for the Department in this |
Section. |
(k) No electric utility shall be deemed to have failed to |
meet the energy efficiency standards to the extent any such |
failure is due to a failure of the Department or the Agency. |
|
(l)(1) The energy efficiency and demand-response plans of |
electric utilities serving more than 500,000 retail customers |
in the State that were approved by the Commission on or before |
the effective date of this amendatory Act of the 99th General |
Assembly for the period June 1, 2014 through May 31, 2017 shall |
continue to be in force and effect through December 31, 2017 so |
that the energy efficiency programs set forth in those plans |
continue to be offered during the period June 1, 2017 through |
December 31, 2017. Each such utility is authorized to |
increase, on a pro rata basis, the energy savings goals and |
budgets approved in its plan to reflect the additional 7 |
months of the plan's operation, provided that such increase |
shall also incorporate reductions to goals and budgets to |
reflect the proportion of the utility's load attributable to |
customers who are exempt from this Section under subsection |
(m) of this Section. |
(2) If an electric utility serving more than 500,000 |
retail customers in the State filed with the Commission, under |
subsection (f) of this Section, its proposed energy efficiency |
and demand-response plan for the period June 1, 2017 through |
May 31, 2020, and the Commission has not yet entered its final |
order approving such plan on or before the effective date of |
this amendatory Act of the 99th General Assembly, then the |
utility shall file a notice of withdrawal with the Commission, |
following such effective date, to withdraw the proposed energy |
efficiency and demand-response plan. Upon receipt of such |
|
notice, the Commission shall dismiss with prejudice any docket |
that had been initiated to investigate such plan, and the plan |
and the record related thereto shall not be the subject of any |
further hearing, investigation, or proceeding of any kind. |
(3) For those electric utilities that serve more than |
500,000 retail customers in the State, this amendatory Act of |
the 99th General Assembly preempts and supersedes any orders |
entered by the Commission that approved such utilities' energy |
efficiency and demand response plans for the period commencing |
June 1, 2017 and ending May 31, 2020. Any such orders shall be |
void, and the provisions of paragraph (1) of this subsection |
(l) shall apply. |
(m) Notwithstanding anything to the contrary, after May |
31, 2017, this Section does not apply to any retail customers |
of an electric utility that serves more than 3,000,000 retail |
customers in the State and whose total highest 30 minute |
demand was more than 10,000 kilowatts, or any retail customers |
of an electric utility that serves less than 3,000,000 retail |
customers but more than 500,000 retail customers in the State |
and whose total highest 15 minute demand was more than 10,000 |
kilowatts. For purposes of this subsection (m), "retail |
customer" has the meaning set forth in Section 16-102 of this |
Act. The criteria for determining whether this subsection (m) |
is applicable to a retail customer shall be based on the 12 |
consecutive billing periods prior to the start of the first |
year of each such multi-year plan. |
|
(Source: P.A. 98-90, eff. 7-15-13; 99-906, eff. 6-1-17 .) |
(220 ILCS 5/8-103B) |
Sec. 8-103B. Energy efficiency and demand-response |
measures. |
(a) It is the policy of the State that electric utilities |
are required to use cost-effective energy efficiency and |
demand-response measures to reduce delivery load. Requiring |
investment in cost-effective energy efficiency and |
demand-response measures will reduce direct and indirect costs |
to consumers by decreasing environmental impacts and by |
avoiding or delaying the need for new generation, |
transmission, and distribution infrastructure. It serves the |
public interest to allow electric utilities to recover costs |
for reasonably and prudently incurred expenditures for energy |
efficiency and demand-response measures. As used in this |
Section, "cost-effective" means that the measures satisfy the |
total resource cost test. The low-income measures described in |
subsection (c) of this Section shall not be required to meet |
the total resource cost test. For purposes of this Section, |
the terms "energy-efficiency", "demand-response", "electric |
utility", and "total resource cost test" have the meanings set |
forth in the Illinois Power Agency Act. "Black, indigenous, |
and people of color" and "BIPOC" means people who are members |
of the groups described in subparagraphs (a) through (e) of |
paragraph (A) of subsection (1) of Section 2 of the Business |
|
Enterprise for Minorities, Women, and Persons with |
Disabilities Act. |
(a-5) This Section applies to electric utilities serving |
more than 500,000 retail customers in the State for those |
multi-year plans commencing after December 31, 2017. |
(b) For purposes of this Section, electric utilities |
subject to this Section that serve more than 3,000,000 retail |
customers in the State shall be deemed to have achieved a |
cumulative persisting annual savings of 6.6% from energy |
efficiency measures and programs implemented during the period |
beginning January 1, 2012 and ending December 31, 2017, which |
percent is based on the deemed average weather normalized |
sales of electric power and energy during calendar years 2014, |
2015, and 2016 of 88,000,000 MWhs. For the purposes of this |
subsection (b) and subsection (b-5), the 88,000,000 MWhs of |
deemed electric power and energy sales shall be reduced by the |
number of MWhs equal to the sum of the annual consumption of |
customers that have opted out of subsections (a) through (j) |
of this Section under paragraph (1) of subsection (l) of this |
Section, as averaged across the calendar years 2014, 2015, and |
2016. After 2017, the deemed value of cumulative persisting |
annual savings from energy efficiency measures and programs |
implemented during the period beginning January 1, 2012 and |
ending December 31, 2017, shall be reduced each year, as |
follows, and the applicable value shall be applied to and |
count toward the utility's achievement of the cumulative |
|
persisting annual savings goals set forth in subsection (b-5): |
(1) 5.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2018; |
(2) 5.2% deemed cumulative persisting annual savings |
for the year ending December 31, 2019; |
(3) 4.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2020; |
(4) 4.0% deemed cumulative persisting annual savings |
for the year ending December 31, 2021; |
(5) 3.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2022; |
(6) 3.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2023; |
(7) 2.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2024; |
(8) 2.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2025; |
(9) 2.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2026; |
(10) 2.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2027; |
(11) 1.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2028; |
(12) 1.7% deemed cumulative persisting annual savings |
for the year ending December 31, 2029; |
(13) 1.5% deemed cumulative persisting annual savings |
|
for the year ending December 31, 2030; |
(14) 1.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2031; |
(15) 1.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2032; |
(16) 0.9% deemed cumulative persisting annual savings |
for the year ending December 31, 2033; |
(17) 0.7% deemed cumulative persisting annual savings |
for the year ending December 31, 2034; |
(18) 0.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2035; |
(19) 0.4% deemed cumulative persisting annual savings |
for the year ending December 31, 2036; |
(20) 0.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2037; |
(21) 0.2% deemed cumulative persisting annual savings |
for the year ending December 31, 2038; |
(22) 0.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2039; and |
(23) 0.0% deemed cumulative persisting annual savings |
for the year ending December 31, 2040 and all subsequent |
years. |
For purposes of this Section, "cumulative persisting |
annual savings" means the total electric energy savings in a |
given year from measures installed in that year or in previous |
years, but no earlier than January 1, 2012, that are still |
|
operational and providing savings in that year because the |
measures have not yet reached the end of their useful lives. |
(b-5) Beginning in 2018, electric utilities subject to |
this Section that serve more than 3,000,000 retail customers |
in the State shall achieve the following cumulative persisting |
annual savings goals, as modified by subsection (f) of this |
Section and as compared to the deemed baseline of 88,000,000 |
MWhs of electric power and energy sales set forth in |
subsection (b), as reduced by the number of MWhs equal to the |
sum of the annual consumption of customers that have opted out |
of subsections (a) through (j) of this Section under paragraph |
(1) of subsection (l) of this Section as averaged across the |
calendar years 2014, 2015, and 2016, through the |
implementation of energy efficiency measures during the |
applicable year and in prior years, but no earlier than |
January 1, 2012: |
(1) 7.8% cumulative persisting annual savings for the |
year ending December 31, 2018; |
(2) 9.1% cumulative persisting annual savings for the |
year ending December 31, 2019; |
(3) 10.4% cumulative persisting annual savings for the |
year ending December 31, 2020; |
(4) 11.8% cumulative persisting annual savings for the |
year ending December 31, 2021; |
(5) 13.1% cumulative persisting annual savings for the |
year ending December 31, 2022; |
|
(6) 14.4% cumulative persisting annual savings for the |
year ending December 31, 2023; |
(7) 15.7% cumulative persisting annual savings for the |
year ending December 31, 2024; |
(8) 17% cumulative persisting annual savings for the |
year ending December 31, 2025; |
(9) 17.9% cumulative persisting annual savings for the |
year ending December 31, 2026; |
(10) 18.8% cumulative persisting annual savings for |
the year ending December 31, 2027; |
(11) 19.7% cumulative persisting annual savings for |
the year ending December 31, 2028; |
(12) 20.6% cumulative persisting annual savings for |
the year ending December 31, 2029; and |
(13) 21.5% cumulative persisting annual savings for |
the year ending December 31, 2030. |
No later than December 31, 2021, the Illinois Commerce |
Commission shall establish additional cumulative persisting |
annual savings goals for the years 2031 through 2035. No later |
than December 31, 2024, the Illinois Commerce Commission shall |
establish additional cumulative persisting annual savings |
goals for the years 2036 through 2040. The Commission shall |
also establish additional cumulative persisting annual savings |
goals every 5 years thereafter to ensure that utilities always |
have goals that extend at least 11 years into the future. The |
cumulative persisting annual savings goals beyond the year |
|
2030 shall increase by 0.9 percentage points per year, absent |
a Commission decision to initiate a proceeding to consider |
establishing goals that increase by more or less than that |
amount. Such a proceeding must be conducted in accordance with |
the procedures described in subsection (f) of this Section. If |
such a proceeding is initiated, the cumulative persisting |
annual savings goals established by the Commission through |
that proceeding shall reflect the Commission's best estimate |
of the maximum amount of additional savings that are forecast |
to be cost-effectively achievable unless such best estimates |
would result in goals that represent less than 0.5 percentage |
point annual increases in total cumulative persisting annual |
savings. The Commission may only establish goals that |
represent less than 0.5 percentage point annual increases in |
cumulative persisting annual savings if it can demonstrate, |
based on clear and convincing evidence and through independent |
analysis, that 0.5 percentage point increases are not |
cost-effectively achievable. The Commission shall inform its |
decision based on an energy efficiency potential study that |
conforms to the requirements of this Section. |
(b-10) For purposes of this Section, electric utilities |
subject to this Section that serve less than 3,000,000 retail |
customers but more than 500,000 retail customers in the State |
shall be deemed to have achieved a cumulative persisting |
annual savings of 6.6% from energy efficiency measures and |
programs implemented during the period beginning January 1, |
|
2012 and ending December 31, 2017, which is based on the deemed |
average weather normalized sales of electric power and energy |
during calendar years 2014, 2015, and 2016 of 36,900,000 MWhs. |
For the purposes of this subsection (b-10) and subsection |
(b-15), the 36,900,000 MWhs of deemed electric power and |
energy sales shall be reduced by the number of MWhs equal to |
the sum of the annual consumption of customers that have opted |
out of subsections (a) through (j) of this Section under |
paragraph (1) of subsection (l) of this Section, as averaged |
across the calendar years 2014, 2015, and 2016. After 2017, |
the deemed value of cumulative persisting annual savings from |
energy efficiency measures and programs implemented during the |
period beginning January 1, 2012 and ending December 31, 2017, |
shall be reduced each year, as follows, and the applicable |
value shall be applied to and count toward the utility's |
achievement of the cumulative persisting annual savings goals |
set forth in subsection (b-15): |
(1) 5.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2018; |
(2) 5.2% deemed cumulative persisting annual savings |
for the year ending December 31, 2019; |
(3) 4.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2020; |
(4) 4.0% deemed cumulative persisting annual savings |
for the year ending December 31, 2021; |
(5) 3.5% deemed cumulative persisting annual savings |
|
for the year ending December 31, 2022; |
(6) 3.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2023; |
(7) 2.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2024; |
(8) 2.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2025; |
(9) 2.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2026; |
(10) 2.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2027; |
(11) 1.8% deemed cumulative persisting annual savings |
for the year ending December 31, 2028; |
(12) 1.7% deemed cumulative persisting annual savings |
for the year ending December 31, 2029; |
(13) 1.5% deemed cumulative persisting annual savings |
for the year ending December 31, 2030; |
(14) 1.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2031; |
(15) 1.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2032; |
(16) 0.9% deemed cumulative persisting annual savings |
for the year ending December 31, 2033; |
(17) 0.7% deemed cumulative persisting annual savings |
for the year ending December 31, 2034; |
(18) 0.5% deemed cumulative persisting annual savings |
|
for the year ending December 31, 2035; |
(19) 0.4% deemed cumulative persisting annual savings |
for the year ending December 31, 2036; |
(20) 0.3% deemed cumulative persisting annual savings |
for the year ending December 31, 2037; |
(21) 0.2% deemed cumulative persisting annual savings |
for the year ending December 31, 2038; |
(22) 0.1% deemed cumulative persisting annual savings |
for the year ending December 31, 2039; and |
(23) 0.0% deemed cumulative persisting annual savings |
for the year ending December 31, 2040 and all subsequent |
years. |
(b-15) Beginning in 2018, electric utilities subject to |
this Section that serve less than 3,000,000 retail customers |
but more than 500,000 retail customers in the State shall |
achieve the following cumulative persisting annual savings |
goals, as modified by subsection (b-20) and subsection (f) of |
this Section and as compared to the deemed baseline as reduced |
by the number of MWhs equal to the sum of the annual |
consumption of customers that have opted out of subsections |
(a) through (j) of this Section under paragraph (1) of |
subsection (l) of this Section as averaged across the calendar |
years 2014, 2015, and 2016, through the implementation of |
energy efficiency measures during the applicable year and in |
prior years, but no earlier than January 1, 2012: |
(1) 7.4% cumulative persisting annual savings for the |
|
year ending December 31, 2018; |
(2) 8.2% cumulative persisting annual savings for the |
year ending December 31, 2019; |
(3) 9.0% cumulative persisting annual savings for the |
year ending December 31, 2020; |
(4) 9.8% cumulative persisting annual savings for the |
year ending December 31, 2021; |
(5) 10.6% cumulative persisting annual savings for the |
year ending December 31, 2022; |
(6) 11.4% cumulative persisting annual savings for the |
year ending December 31, 2023; |
(7) 12.2% cumulative persisting annual savings for the |
year ending December 31, 2024; |
(8) 13% cumulative persisting annual savings for the |
year ending December 31, 2025; |
(9) 13.6% cumulative persisting annual savings for the |
year ending December 31, 2026; |
(10) 14.2% cumulative persisting annual savings for |
the year ending December 31, 2027; |
(11) 14.8% cumulative persisting annual savings for |
the year ending December 31, 2028; |
(12) 15.4% cumulative persisting annual savings for |
the year ending December 31, 2029; and |
(13) 16% cumulative persisting annual savings for the |
year ending December 31, 2030. |
No later than December 31, 2021, the Illinois Commerce |
|
Commission shall establish additional cumulative persisting |
annual savings goals for the years 2031 through 2035. No later |
than December 31, 2024, the Illinois Commerce Commission shall |
establish additional cumulative persisting annual savings |
goals for the years 2036 through 2040. The Commission shall |
also establish additional cumulative persisting annual savings |
goals every 5 years thereafter to ensure that utilities always |
have goals that extend at least 11 years into the future. The |
cumulative persisting annual savings goals beyond the year |
2030 shall increase by 0.6 percentage points per year, absent |
a Commission decision to initiate a proceeding to consider |
establishing goals that increase by more or less than that |
amount. Such a proceeding must be conducted in accordance with |
the procedures described in subsection (f) of this Section. If |
such a proceeding is initiated, the cumulative persisting |
annual savings goals established by the Commission through |
that proceeding shall reflect the Commission's best estimate |
of the maximum amount of additional savings that are forecast |
to be cost-effectively achievable unless such best estimates |
would result in goals that represent less than 0.4 percentage |
point annual increases in total cumulative persisting annual |
savings. The Commission may only establish goals that |
represent less than 0.4 percentage point annual increases in |
cumulative persisting annual savings if it can demonstrate, |
based on clear and convincing evidence and through independent |
analysis, that 0.4 percentage point increases are not |
|
cost-effectively achievable. The Commission shall inform its |
decision based on an energy efficiency potential study that |
conforms to the requirements of this Section. |
(b-20) Each electric utility subject to this Section may |
include cost-effective voltage optimization measures in its |
plans submitted under subsections (f) and (g) of this Section, |
and the costs incurred by a utility to implement the measures |
under a Commission-approved plan shall be recovered under the |
provisions of Article IX or Section 16-108.5 of this Act. For |
purposes of this Section, the measure life of voltage |
optimization measures shall be 15 years. The measure life |
period is independent of the depreciation rate of the voltage |
optimization assets deployed. Utilities may claim savings from |
voltage optimization on circuits for more than 15 years if |
they can demonstrate that they have made additional |
investments necessary to enable voltage optimization savings |
to continue beyond 15 years. Such demonstrations must be |
subject to the review of independent evaluation. |
Within 270 days after June 1, 2017 (the effective date of |
Public Act 99-906), an electric utility that serves less than |
3,000,000 retail customers but more than 500,000 retail |
customers in the State shall file a plan with the Commission |
that identifies the cost-effective voltage optimization |
investment the electric utility plans to undertake through |
December 31, 2024. The Commission, after notice and hearing, |
shall approve or approve with modification the plan within 120 |
|
days after the plan's filing and, in the order approving or |
approving with modification the plan, the Commission shall |
adjust the applicable cumulative persisting annual savings |
goals set forth in subsection (b-15) to reflect any amount of |
cost-effective energy savings approved by the Commission that |
is greater than or less than the following cumulative |
persisting annual savings values attributable to voltage |
optimization for the applicable year: |
(1) 0.0% of cumulative persisting annual savings for |
the year ending December 31, 2018; |
(2) 0.17% of cumulative persisting annual savings for |
the year ending December 31, 2019; |
(3) 0.17% of cumulative persisting annual savings for |
the year ending December 31, 2020; |
(4) 0.33% of cumulative persisting annual savings for |
the year ending December 31, 2021; |
(5) 0.5% of cumulative persisting annual savings for |
the year ending December 31, 2022; |
(6) 0.67% of cumulative persisting annual savings for |
the year ending December 31, 2023; |
(7) 0.83% of cumulative persisting annual savings for |
the year ending December 31, 2024; and |
(8) 1.0% of cumulative persisting annual savings for |
the year ending December 31, 2025 and all subsequent |
years. |
(b-25) In the event an electric utility jointly offers an |
|
energy efficiency measure or program with a gas utility under |
plans approved under this Section and Section 8-104 of this |
Act, the electric utility may continue offering the program, |
including the gas energy efficiency measures, in the event the |
gas utility discontinues funding the program. In that event, |
the energy savings value associated with such other fuels |
shall be converted to electric energy savings on an equivalent |
Btu basis for the premises. However, the electric utility |
shall prioritize programs for low-income residential customers |
to the extent practicable. An electric utility may recover the |
costs of offering the gas energy efficiency measures under |
this subsection (b-25). |
For those energy efficiency measures or programs that save |
both electricity and other fuels but are not jointly offered |
with a gas utility under plans approved under this Section and |
Section 8-104 or not offered with an affiliated gas utility |
under paragraph (6) of subsection (f) of Section 8-104 of this |
Act, the electric utility may count savings of fuels other |
than electricity toward the achievement of its annual savings |
goal, and the energy savings value associated with such other |
fuels shall be converted to electric energy savings on an |
equivalent Btu basis at the premises. |
In no event shall more than 10% of each year's applicable |
annual total savings requirement as defined in paragraph (7.5) |
of subsection (g) of this Section be met through savings of |
fuels other than electricity. |
|
(b-27) Beginning in 2022, an electric utility may offer |
and promote measures that electrify space heating, water |
heating, cooling, drying, cooking, industrial processes, and |
other building and industrial end uses that would otherwise be |
served by combustion of fossil fuel at the premises, provided |
that the electrification measures reduce total energy |
consumption at the premises. The electric utility may count |
the reduction in energy consumption at the premises toward |
achievement of its annual savings goals. The reduction in |
energy consumption at the premises shall be calculated as the |
difference between: (A) the reduction in Btu consumption of |
fossil fuels as a result of electrification, converted to |
kilowatt-hour equivalents by dividing by 3,412 Btus per |
kilowatt hour; and (B) the increase in kilowatt hours of |
electricity consumption resulting from the displacement of |
fossil fuel consumption as a result of electrification. An |
electric utility may recover the costs of offering and |
promoting electrification measures under this subsection |
(b-27). |
In no event shall electrification savings counted toward |
each year's applicable annual total savings requirement, as |
defined in paragraph (7.5) of subsection (g) of this Section, |
be greater than: |
(1) 5% per year for each year from 2022 through 2025; |
(2) 10% per year for each year from 2026 through 2029; |
and |
|
(3) 15% per year for 2030 and all subsequent years. |
In addition, a minimum of 25% of all electrification savings |
counted toward a utility's applicable annual total savings |
requirement must be from electrification of end uses in |
low-income housing. The limitations on electrification savings |
that may be counted toward a utility's annual savings goals |
are separate from and in addition to the subsection (b-25) |
limitations governing the counting of the other fuel savings |
resulting from efficiency measures and programs. |
As part of the annual informational filing to the |
Commission that is required under paragraph (9) of subsection |
(g) of this Section, each utility shall identify the specific |
electrification measures offered under this subsection (b-27); |
the quantity of each electrification measure that was |
installed by its customers; the average total cost, average |
utility cost, average reduction in fossil fuel consumption, |
and average increase in electricity consumption associated |
with each electrification measure; the portion of |
installations of each electrification measure that were in |
low-income single-family housing, low-income multifamily |
housing, non-low-income single-family housing, non-low-income |
multifamily housing, commercial buildings, and industrial |
facilities; and the quantity of savings associated with each |
measure category in each customer category that are being |
counted toward the utility's applicable annual total savings |
requirement. Prior to installing an electrification measure, |
|
the utility shall provide a customer with an estimate of the |
impact of the new measure on the customer's average monthly |
electric bill and total annual energy expenses. |
(c) Electric utilities shall be responsible for overseeing |
the design, development, and filing of energy efficiency plans |
with the Commission and may, as part of that implementation, |
outsource various aspects of program development and |
implementation. A minimum of 10%, for electric utilities that |
serve more than 3,000,000 retail customers in the State, and a |
minimum of 7%, for electric utilities that serve less than |
3,000,000 retail customers but more than 500,000 retail |
customers in the State, of the utility's entire portfolio |
funding level for a given year shall be used to procure |
cost-effective energy efficiency measures from units of local |
government, municipal corporations, school districts, public |
housing, public institutions of higher education, and |
community college districts, provided that a minimum |
percentage of available funds shall be used to procure energy |
efficiency from public housing, which percentage shall be |
equal to public housing's share of public building energy |
consumption. |
The utilities shall also implement energy efficiency |
measures targeted at low-income households, which, for |
purposes of this Section, shall be defined as households at or |
below 80% of area median income, and expenditures to implement |
the measures shall be no less than $40,000,000 per year for |
|
electric utilities that serve more than 3,000,000 retail |
customers in the State and no less than $13,000,000 per year |
for electric utilities that serve less than 3,000,000 retail |
customers but more than 500,000 retail customers in the State. |
The ratio of spending on efficiency programs targeted at |
low-income multifamily buildings to spending on efficiency |
programs targeted at low-income single-family buildings shall |
be designed to achieve levels of savings from each building |
type that are approximately proportional to the magnitude of |
cost-effective lifetime savings potential in each building |
type. Investment in low-income whole-building weatherization |
programs shall constitute a minimum of 80% of a utility's |
total budget specifically dedicated to serving low-income |
customers. |
The utilities shall work to bundle low-income energy |
efficiency offerings with other programs that serve low-income |
households to maximize the benefits going to these households. |
The utilities shall market and implement low-income energy |
efficiency programs in coordination with low-income assistance |
programs, the Illinois Solar for All Program, and |
weatherization whenever practicable. The program implementer |
shall walk the customer through the enrollment process for any |
programs for which the customer is eligible. The utilities |
shall also pilot targeting customers with high arrearages, |
high energy intensity (ratio of energy usage divided by home |
or unit square footage), or energy assistance programs with |
|
energy efficiency offerings, and then track reduction in |
arrearages as a result of the targeting. This targeting and |
bundling of low-income energy programs shall be offered to |
both low-income single-family and multifamily customers |
(owners and residents). |
The utilities shall invest in health and safety measures |
appropriate and necessary for comprehensively weatherizing a |
home or multifamily building, and shall implement a health and |
safety fund of at least 15% of the total income-qualified |
weatherization budget that shall be used for the purpose of |
making grants for technical assistance, construction, |
reconstruction, improvement, or repair of buildings to |
facilitate their participation in the energy efficiency |
programs targeted at low-income single-family and multifamily |
households. These funds may also be used for the purpose of |
making grants for technical assistance, construction, |
reconstruction, improvement, or repair of the following |
buildings to facilitate their participation in the energy |
efficiency programs created by this Section: (1) buildings |
that are owned or operated by registered 501(c)(3) public |
charities; and (2) day care centers, day care homes, or group |
day care homes, as defined under 89 Ill. Adm. Code Part 406, |
407, or 408, respectively. |
Each electric utility shall assess opportunities to |
implement cost-effective energy efficiency measures and |
programs through a public housing authority or authorities |
|
located in its service territory. If such opportunities are |
identified, the utility shall propose such measures and |
programs to address the opportunities. Expenditures to address |
such opportunities shall be credited toward the minimum |
procurement and expenditure requirements set forth in this |
subsection (c). |
Implementation of energy efficiency measures and programs |
targeted at low-income households should be contracted, when |
it is practicable, to independent third parties that have |
demonstrated capabilities to serve such households, with a |
preference for not-for-profit entities and government agencies |
that have existing relationships with or experience serving |
low-income communities in the State. |
Each electric utility shall develop and implement |
reporting procedures that address and assist in determining |
the amount of energy savings that can be applied to the |
low-income procurement and expenditure requirements set forth |
in this subsection (c). Each electric utility shall also track |
the types and quantities or volumes of insulation and air |
sealing materials, and their associated energy saving |
benefits, installed in energy efficiency programs targeted at |
low-income single-family and multifamily households. |
The electric utilities shall participate in a low-income |
energy efficiency accountability committee ("the committee"), |
which will directly inform the design, implementation, and |
evaluation of the low-income and public-housing energy |
|
efficiency programs. The committee shall be comprised of the |
electric utilities subject to the requirements of this |
Section, the gas utilities subject to the requirements of |
Section 8-104 of this Act, the utilities' low-income energy |
efficiency implementation contractors, nonprofit |
organizations, community action agencies, advocacy groups, |
State and local governmental agencies, public-housing |
organizations, and representatives of community-based |
organizations, especially those living in or working with |
environmental justice communities and BIPOC communities. The |
committee shall be composed of 2 geographically differentiated |
subcommittees: one for stakeholders in northern Illinois and |
one for stakeholders in central and southern Illinois. The |
subcommittees shall meet together at least twice per year. |
There shall be one statewide leadership committee led by |
and composed of community-based organizations that are |
representative of BIPOC and environmental justice communities |
and that includes equitable representation from BIPOC |
communities. The leadership committee shall be composed of an |
equal number of representatives from the 2 subcommittees. The |
subcommittees shall address specific programs and issues, with |
the leadership committee convening targeted workgroups as |
needed. The leadership committee may elect to work with an |
independent facilitator to solicit and organize feedback, |
recommendations and meeting participation from a wide variety |
of community-based stakeholders. If a facilitator is used, |
|
they shall be fair and responsive to the needs of all |
stakeholders involved in the committee. |
All committee meetings must be accessible, with rotating |
locations if meetings are held in-person, virtual |
participation options, and materials and agendas circulated in |
advance. |
There shall also be opportunities for direct input by |
committee members outside of committee meetings, such as via |
individual meetings, surveys, emails and calls, to ensure |
robust participation by stakeholders with limited capacity and |
ability to attend committee meetings. Committee meetings shall |
emphasize opportunities to bundle and coordinate delivery of |
low-income energy efficiency with other programs that serve |
low-income communities, such as the Illinois Solar for All |
Program and bill payment assistance programs. Meetings shall |
include educational opportunities for stakeholders to learn |
more about these additional offerings, and the committee shall |
assist in figuring out the best methods for coordinated |
delivery and implementation of offerings when serving |
low-income communities. The committee shall directly and |
equitably influence and inform utility low-income and |
public-housing energy efficiency programs and priorities. |
Participating utilities shall implement recommendations from |
the committee whenever possible. |
Participating utilities shall track and report how input |
from the committee has led to new approaches and changes in |
|
their energy efficiency portfolios. This reporting shall occur |
at committee meetings and in quarterly energy efficiency |
reports to the Stakeholder Advisory Group and Illinois |
Commerce Commission, and other relevant reporting mechanisms. |
Participating utilities shall also report on relevant equity |
data and metrics requested by the committee, such as energy |
burden data, geographic, racial, and other relevant |
demographic data on where programs are being delivered and |
what populations programs are serving. |
The Illinois Commerce Commission shall oversee and have |
relevant staff participate in the committee. The committee |
shall have a budget of 0.25% of each utility's entire |
efficiency portfolio funding for a given year. The budget |
shall be overseen by the Commission. The budget shall be used |
to provide grants for community-based organizations serving on |
the leadership committee, stipends for community-based |
organizations participating in the committee, grants for |
community-based organizations to do energy efficiency outreach |
and education, and relevant meeting needs as determined by the |
leadership committee. The education and outreach shall |
include, but is not limited to, basic energy efficiency |
education, information about low-income energy efficiency |
programs, and information on the committee's purpose, |
structure, and activities. |
(d) Notwithstanding any other provision of law to the |
contrary, a utility providing approved energy efficiency |
|
measures and, if applicable, demand-response measures in the |
State shall be permitted to recover all reasonable and |
prudently incurred costs of those measures from all retail |
customers, except as provided in subsection (l) of this |
Section, as follows, provided that nothing in this subsection |
(d) permits the double recovery of such costs from customers: |
(1) The utility may recover its costs through an |
automatic adjustment clause tariff filed with and approved |
by the Commission. The tariff shall be established outside |
the context of a general rate case. Each year the |
Commission shall initiate a review to reconcile any |
amounts collected with the actual costs and to determine |
the required adjustment to the annual tariff factor to |
match annual expenditures. To enable the financing of the |
incremental capital expenditures, including regulatory |
assets, for electric utilities that serve less than |
3,000,000 retail customers but more than 500,000 retail |
customers in the State, the utility's actual year-end |
capital structure that includes a common equity ratio, |
excluding goodwill, of up to and including 50% of the |
total capital structure shall be deemed reasonable and |
used to set rates. |
(2) A utility may recover its costs through an energy |
efficiency formula rate approved by the Commission under a |
filing under subsections (f) and (g) of this Section, |
which shall specify the cost components that form the |
|
basis of the rate charged to customers with sufficient |
specificity to operate in a standardized manner and be |
updated annually with transparent information that |
reflects the utility's actual costs to be recovered during |
the applicable rate year, which is the period beginning |
with the first billing day of January and extending |
through the last billing day of the following December. |
The energy efficiency formula rate shall be implemented |
through a tariff filed with the Commission under |
subsections (f) and (g) of this Section that is consistent |
with the provisions of this paragraph (2) and that shall |
be applicable to all delivery services customers. The |
Commission shall conduct an investigation of the tariff in |
a manner consistent with the provisions of this paragraph |
(2), subsections (f) and (g) of this Section, and the |
provisions of Article IX of this Act to the extent they do |
not conflict with this paragraph (2). The energy |
efficiency formula rate approved by the Commission shall |
remain in effect at the discretion of the utility and |
shall do the following: |
(A) Provide for the recovery of the utility's |
actual costs incurred under this Section that are |
prudently incurred and reasonable in amount consistent |
with Commission practice and law. The sole fact that a |
cost differs from that incurred in a prior calendar |
year or that an investment is different from that made |
|
in a prior calendar year shall not imply the |
imprudence or unreasonableness of that cost or |
investment. |
(B) Reflect the utility's actual year-end capital |
structure for the applicable calendar year, excluding |
goodwill, subject to a determination of prudence and |
reasonableness consistent with Commission practice and |
law. To enable the financing of the incremental |
capital expenditures, including regulatory assets, for |
electric utilities that serve less than 3,000,000 |
retail customers but more than 500,000 retail |
customers in the State, a participating electric |
utility's actual year-end capital structure that |
includes a common equity ratio, excluding goodwill, of |
up to and including 50% of the total capital structure |
shall be deemed reasonable and used to set rates. |
(C) Include a cost of equity, which shall be |
calculated as the sum of the following: |
(i) the average for the applicable calendar |
year of the monthly average yields of 30-year U.S. |
Treasury bonds published by the Board of Governors |
of the Federal Reserve System in its weekly H.15 |
Statistical Release or successor publication; and |
(ii) 580 basis points. |
At such time as the Board of Governors of the |
Federal Reserve System ceases to include the monthly |
|
average yields of 30-year U.S. Treasury bonds in its |
weekly H.15 Statistical Release or successor |
publication, the monthly average yields of the U.S. |
Treasury bonds then having the longest duration |
published by the Board of Governors in its weekly H.15 |
Statistical Release or successor publication shall |
instead be used for purposes of this paragraph (2). |
(D) Permit and set forth protocols, subject to a |
determination of prudence and reasonableness |
consistent with Commission practice and law, for the |
following: |
(i) recovery of incentive compensation expense |
that is based on the achievement of operational |
metrics, including metrics related to budget |
controls, outage duration and frequency, safety, |
customer service, efficiency and productivity, and |
environmental compliance; however, this protocol |
shall not apply if such expense related to costs |
incurred under this Section is recovered under |
Article IX or Section 16-108.5 of this Act; |
incentive compensation expense that is based on |
net income or an affiliate's earnings per share |
shall not be recoverable under the energy |
efficiency formula rate; |
(ii) recovery of pension and other |
post-employment benefits expense, provided that |
|
such costs are supported by an actuarial study; |
however, this protocol shall not apply if such |
expense related to costs incurred under this |
Section is recovered under Article IX or Section |
16-108.5 of this Act; |
(iii) recovery of existing regulatory assets |
over the periods previously authorized by the |
Commission; |
(iv) as described in subsection (e), |
amortization of costs incurred under this Section; |
and |
(v) projected, weather normalized billing |
determinants for the applicable rate year. |
(E) Provide for an annual reconciliation, as |
described in paragraph (3) of this subsection (d), |
less any deferred taxes related to the reconciliation, |
with interest at an annual rate of return equal to the |
utility's weighted average cost of capital, including |
a revenue conversion factor calculated to recover or |
refund all additional income taxes that may be payable |
or receivable as a result of that return, of the energy |
efficiency revenue requirement reflected in rates for |
each calendar year, beginning with the calendar year |
in which the utility files its energy efficiency |
formula rate tariff under this paragraph (2), with |
what the revenue requirement would have been had the |
|
actual cost information for the applicable calendar |
year been available at the filing date. |
The utility shall file, together with its tariff, the |
projected costs to be incurred by the utility during the |
rate year under the utility's multi-year plan approved |
under subsections (f) and (g) of this Section, including, |
but not limited to, the projected capital investment costs |
and projected regulatory asset balances with |
correspondingly updated depreciation and amortization |
reserves and expense, that shall populate the energy |
efficiency formula rate and set the initial rates under |
the formula. |
The Commission shall review the proposed tariff in |
conjunction with its review of a proposed multi-year plan, |
as specified in paragraph (5) of subsection (g) of this |
Section. The review shall be based on the same evidentiary |
standards, including, but not limited to, those concerning |
the prudence and reasonableness of the costs incurred by |
the utility, the Commission applies in a hearing to review |
a filing for a general increase in rates under Article IX |
of this Act. The initial rates shall take effect beginning |
with the January monthly billing period following the |
Commission's approval. |
The tariff's rate design and cost allocation across |
customer classes shall be consistent with the utility's |
automatic adjustment clause tariff in effect on June 1, |
|
2017 (the effective date of Public Act 99-906); however, |
the Commission may revise the tariff's rate design and |
cost allocation in subsequent proceedings under paragraph |
(3) of this subsection (d). |
If the energy efficiency formula rate is terminated, |
the then current rates shall remain in effect until such |
time as the energy efficiency costs are incorporated into |
new rates that are set under this subsection (d) or |
Article IX of this Act, subject to retroactive rate |
adjustment, with interest, to reconcile rates charged with |
actual costs. |
(3) The provisions of this paragraph (3) shall only |
apply to an electric utility that has elected to file an |
energy efficiency formula rate under paragraph (2) of this |
subsection (d). Subsequent to the Commission's issuance of |
an order approving the utility's energy efficiency formula |
rate structure and protocols, and initial rates under |
paragraph (2) of this subsection (d), the utility shall |
file, on or before June 1 of each year, with the Chief |
Clerk of the Commission its updated cost inputs to the |
energy efficiency formula rate for the applicable rate |
year and the corresponding new charges, as well as the |
information described in paragraph (9) of subsection (g) |
of this Section. Each such filing shall conform to the |
following requirements and include the following |
information: |
|
(A) The inputs to the energy efficiency formula |
rate for the applicable rate year shall be based on the |
projected costs to be incurred by the utility during |
the rate year under the utility's multi-year plan |
approved under subsections (f) and (g) of this |
Section, including, but not limited to, projected |
capital investment costs and projected regulatory |
asset balances with correspondingly updated |
depreciation and amortization reserves and expense. |
The filing shall also include a reconciliation of the |
energy efficiency revenue requirement that was in |
effect for the prior rate year (as set by the cost |
inputs for the prior rate year) with the actual |
revenue requirement for the prior rate year |
(determined using a year-end rate base) that uses |
amounts reflected in the applicable FERC Form 1 that |
reports the actual costs for the prior rate year. Any |
over-collection or under-collection indicated by such |
reconciliation shall be reflected as a credit against, |
or recovered as an additional charge to, respectively, |
with interest calculated at a rate equal to the |
utility's weighted average cost of capital approved by |
the Commission for the prior rate year, the charges |
for the applicable rate year. Such over-collection or |
under-collection shall be adjusted to remove any |
deferred taxes related to the reconciliation, for |
|
purposes of calculating interest at an annual rate of |
return equal to the utility's weighted average cost of |
capital approved by the Commission for the prior rate |
year, including a revenue conversion factor calculated |
to recover or refund all additional income taxes that |
may be payable or receivable as a result of that |
return. Each reconciliation shall be certified by the |
participating utility in the same manner that FERC |
Form 1 is certified. The filing shall also include the |
charge or credit, if any, resulting from the |
calculation required by subparagraph (E) of paragraph |
(2) of this subsection (d). |
Notwithstanding any other provision of law to the |
contrary, the intent of the reconciliation is to |
ultimately reconcile both the revenue requirement |
reflected in rates for each calendar year, beginning |
with the calendar year in which the utility files its |
energy efficiency formula rate tariff under paragraph |
(2) of this subsection (d), with what the revenue |
requirement determined using a year-end rate base for |
the applicable calendar year would have been had the |
actual cost information for the applicable calendar |
year been available at the filing date. |
For purposes of this Section, "FERC Form 1" means |
the Annual Report of Major Electric Utilities, |
Licensees and Others that electric utilities are |
|
required to file with the Federal Energy Regulatory |
Commission under the Federal Power Act, Sections 3, |
4(a), 304 and 209, modified as necessary to be |
consistent with 83 Ill. Adm. Code Part 415 as of May 1, |
2011. Nothing in this Section is intended to allow |
costs that are not otherwise recoverable to be |
recoverable by virtue of inclusion in FERC Form 1. |
(B) The new charges shall take effect beginning on |
the first billing day of the following January billing |
period and remain in effect through the last billing |
day of the next December billing period regardless of |
whether the Commission enters upon a hearing under |
this paragraph (3). |
(C) The filing shall include relevant and |
necessary data and documentation for the applicable |
rate year. Normalization adjustments shall not be |
required. |
Within 45 days after the utility files its annual |
update of cost inputs to the energy efficiency formula |
rate, the Commission shall with reasonable notice, |
initiate a proceeding concerning whether the projected |
costs to be incurred by the utility and recovered during |
the applicable rate year, and that are reflected in the |
inputs to the energy efficiency formula rate, are |
consistent with the utility's approved multi-year plan |
under subsections (f) and (g) of this Section and whether |
|
the costs incurred by the utility during the prior rate |
year were prudent and reasonable. The Commission shall |
also have the authority to investigate the information and |
data described in paragraph (9) of subsection (g) of this |
Section, including the proposed adjustment to the |
utility's return on equity component of its weighted |
average cost of capital. During the course of the |
proceeding, each objection shall be stated with |
particularity and evidence provided in support thereof, |
after which the utility shall have the opportunity to |
rebut the evidence. Discovery shall be allowed consistent |
with the Commission's Rules of Practice, which Rules of |
Practice shall be enforced by the Commission or the |
assigned administrative law judge. The Commission shall |
apply the same evidentiary standards, including, but not |
limited to, those concerning the prudence and |
reasonableness of the costs incurred by the utility, |
during the proceeding as it would apply in a proceeding to |
review a filing for a general increase in rates under |
Article IX of this Act. The Commission shall not, however, |
have the authority in a proceeding under this paragraph |
(3) to consider or order any changes to the structure or |
protocols of the energy efficiency formula rate approved |
under paragraph (2) of this subsection (d). In a |
proceeding under this paragraph (3), the Commission shall |
enter its order no later than the earlier of 195 days after |
|
the utility's filing of its annual update of cost inputs |
to the energy efficiency formula rate or December 15. The |
utility's proposed return on equity calculation, as |
described in paragraphs (7) through (9) of subsection (g) |
of this Section, shall be deemed the final, approved |
calculation on December 15 of the year in which it is filed |
unless the Commission enters an order on or before |
December 15, after notice and hearing, that modifies such |
calculation consistent with this Section. The Commission's |
determinations of the prudence and reasonableness of the |
costs incurred, and determination of such return on equity |
calculation, for the applicable calendar year shall be |
final upon entry of the Commission's order and shall not |
be subject to reopening, reexamination, or collateral |
attack in any other Commission proceeding, case, docket, |
order, rule, or regulation; however, nothing in this |
paragraph (3) shall prohibit a party from petitioning the |
Commission to rehear or appeal to the courts the order |
under the provisions of this Act. |
(e) Beginning on June 1, 2017 (the effective date of |
Public Act 99-906), a utility subject to the requirements of |
this Section may elect to defer, as a regulatory asset, up to |
the full amount of its expenditures incurred under this |
Section for each annual period, including, but not limited to, |
any expenditures incurred above the funding level set by |
subsection (f) of this Section for a given year. The total |
|
expenditures deferred as a regulatory asset in a given year |
shall be amortized and recovered over a period that is equal to |
the weighted average of the energy efficiency measure lives |
implemented for that year that are reflected in the regulatory |
asset. The unamortized balance shall be recognized as of |
December 31 for a given year. The utility shall also earn a |
return on the total of the unamortized balances of all of the |
energy efficiency regulatory assets, less any deferred taxes |
related to those unamortized balances, at an annual rate equal |
to the utility's weighted average cost of capital that |
includes, based on a year-end capital structure, the utility's |
actual cost of debt for the applicable calendar year and a cost |
of equity, which shall be calculated as the sum of the (i) the |
average for the applicable calendar year of the monthly |
average yields of 30-year U.S. Treasury bonds published by the |
Board of Governors of the Federal Reserve System in its weekly |
H.15 Statistical Release or successor publication; and (ii) |
580 basis points, including a revenue conversion factor |
calculated to recover or refund all additional income taxes |
that may be payable or receivable as a result of that return. |
Capital investment costs shall be depreciated and recovered |
over their useful lives consistent with generally accepted |
accounting principles. The weighted average cost of capital |
shall be applied to the capital investment cost balance, less |
any accumulated depreciation and accumulated deferred income |
taxes, as of December 31 for a given year. |
|
When an electric utility creates a regulatory asset under |
the provisions of this Section, the costs are recovered over a |
period during which customers also receive a benefit which is |
in the public interest. Accordingly, it is the intent of the |
General Assembly that an electric utility that elects to |
create a regulatory asset under the provisions of this Section |
shall recover all of the associated costs as set forth in this |
Section. After the Commission has approved the prudence and |
reasonableness of the costs that comprise the regulatory |
asset, the electric utility shall be permitted to recover all |
such costs, and the value and recoverability through rates of |
the associated regulatory asset shall not be limited, altered, |
impaired, or reduced. |
(f) Beginning in 2017, each electric utility shall file an |
energy efficiency plan with the Commission to meet the energy |
efficiency standards for the next applicable multi-year period |
beginning January 1 of the year following the filing, |
according to the schedule set forth in paragraphs (1) through |
(3) of this subsection (f). If a utility does not file such a |
plan on or before the applicable filing deadline for the plan, |
it shall face a penalty of $100,000 per day until the plan is |
filed. |
(1) No later than 30 days after June 1, 2017 (the |
effective date of Public Act 99-906), each electric |
utility shall file a 4-year energy efficiency plan |
commencing on January 1, 2018 that is designed to achieve |
|
the cumulative persisting annual savings goals specified |
in paragraphs (1) through (4) of subsection (b-5) of this |
Section or in paragraphs (1) through (4) of subsection |
(b-15) of this Section, as applicable, through |
implementation of energy efficiency measures; however, the |
goals may be reduced if the utility's expenditures are |
limited pursuant to subsection (m) of this Section or, for |
a utility that serves less than 3,000,000 retail |
customers, if each of the following conditions are met: |
(A) the plan's analysis and forecasts of the utility's |
ability to acquire energy savings demonstrate that |
achievement of such goals is not cost effective; and (B) |
the amount of energy savings achieved by the utility as |
determined by the independent evaluator for the most |
recent year for which savings have been evaluated |
preceding the plan filing was less than the average annual |
amount of savings required to achieve the goals for the |
applicable 4-year plan period. Except as provided in |
subsection (m) of this Section, annual increases in |
cumulative persisting annual savings goals during the |
applicable 4-year plan period shall not be reduced to |
amounts that are less than the maximum amount of |
cumulative persisting annual savings that is forecast to |
be cost-effectively achievable during the 4-year plan |
period. The Commission shall review any proposed goal |
reduction as part of its review and approval of the |
|
utility's proposed plan. |
(2) No later than March 1, 2021, each electric utility |
shall file a 4-year energy efficiency plan commencing on |
January 1, 2022 that is designed to achieve the cumulative |
persisting annual savings goals specified in paragraphs |
(5) through (8) of subsection (b-5) of this Section or in |
paragraphs (5) through (8) of subsection (b-15) of this |
Section, as applicable, through implementation of energy |
efficiency measures; however, the goals may be reduced if |
either (1) clear and convincing evidence demonstrates, |
through independent analysis, that the expenditure limits |
in subsection (m) of this Section preclude full |
achievement of the goals or (2) each of the following |
conditions are met: (A) the plan's analysis and forecasts |
of the utility's ability to acquire energy savings |
demonstrate by clear and convincing evidence and through |
independent analysis that achievement of such goals is not |
cost effective; and (B) the amount of energy savings |
achieved by the utility as determined by the independent |
evaluator for the most recent year for which savings have |
been evaluated preceding the plan filing was less than the |
average annual amount of savings required to achieve the |
goals for the applicable 4-year plan period. If there is |
not clear and convincing evidence that achieving the |
savings goals specified in paragraph (b-5) or (b-15) of |
this Section is possible both cost-effectively and within |
|
the expenditure limits in subsection (m), such savings |
goals shall not be reduced. Except as provided in |
subsection (m) of this Section, annual increases in |
cumulative persisting annual savings goals during the |
applicable 4-year plan period shall not be reduced to |
amounts that are less than the maximum amount of |
cumulative persisting annual savings that is forecast to |
be cost-effectively achievable during the 4-year plan |
period. The Commission shall review any proposed goal |
reduction as part of its review and approval of the |
utility's proposed plan. |
(3) No later than March 1, 2025, each electric utility |
shall file a 4-year energy efficiency plan commencing on |
January 1, 2026 that is designed to achieve the cumulative |
persisting annual savings goals specified in paragraphs |
(9) through (12) of subsection (b-5) of this Section or in |
paragraphs (9) through (12) of subsection (b-15) of this |
Section, as applicable, through implementation of energy |
efficiency measures; however, the goals may be reduced if |
either (1) clear and convincing evidence demonstrates, |
through independent analysis, that the expenditure limits |
in subsection (m) of this Section preclude full |
achievement of the goals or (2) each of the following |
conditions are met: (A) the plan's analysis and forecasts |
of the utility's ability to acquire energy savings |
demonstrate by clear and convincing evidence and through |
|
independent analysis that achievement of such goals is not |
cost effective; and (B) the amount of energy savings |
achieved by the utility as determined by the independent |
evaluator for the most recent year for which savings have |
been evaluated preceding the plan filing was less than the |
average annual amount of savings required to achieve the |
goals for the applicable 4-year plan period. If there is |
not clear and convincing evidence that achieving the |
savings goals specified in paragraphs (b-5) or (b-15) of |
this Section is possible both cost-effectively and within |
the expenditure limits in subsection (m), such savings |
goals shall not be reduced. Except as provided in |
subsection (m) of this Section, annual increases in |
cumulative persisting annual savings goals during the |
applicable 4-year plan period shall not be reduced to |
amounts that are less than the maximum amount of |
cumulative persisting annual savings that is forecast to |
be cost-effectively achievable during the 4-year plan |
period. The Commission shall review any proposed goal |
reduction as part of its review and approval of the |
utility's proposed plan. |
(4) No later than March 1, 2029, and every 4 years |
thereafter, each electric utility shall file a 4-year |
energy efficiency plan commencing on January 1, 2030, and |
every 4 years thereafter, respectively, that is designed |
to achieve the cumulative persisting annual savings goals |
|
established by the Illinois Commerce Commission pursuant |
to direction of subsections (b-5) and (b-15) of this |
Section, as applicable, through implementation of energy |
efficiency measures; however, the goals may be reduced if |
either (1) clear and convincing evidence and independent |
analysis demonstrates that the expenditure limits in |
subsection (m) of this Section preclude full achievement |
of the goals or (2) each of the following conditions are |
met: (A) the plan's analysis and forecasts of the |
utility's ability to acquire energy savings demonstrate by |
clear and convincing evidence and through independent |
analysis that achievement of such goals is not |
cost-effective; and (B) the amount of energy savings |
achieved by the utility as determined by the independent |
evaluator for the most recent year for which savings have |
been evaluated preceding the plan filing was less than the |
average annual amount of savings required to achieve the |
goals for the applicable 4-year plan period. If there is |
not clear and convincing evidence that achieving the |
savings goals specified in paragraphs (b-5) or (b-15) of |
this Section is possible both cost-effectively and within |
the expenditure limits in subsection (m), such savings |
goals shall not be reduced. Except as provided in |
subsection (m) of this Section, annual increases in |
cumulative persisting annual savings goals during the |
applicable 4-year plan period shall not be reduced to |
|
amounts that are less than the maximum amount of |
cumulative persisting annual savings that is forecast to |
be cost-effectively achievable during the 4-year plan |
period. The Commission shall review any proposed goal |
reduction as part of its review and approval of the |
utility's proposed plan. |
Each utility's plan shall set forth the utility's |
proposals to meet the energy efficiency standards identified |
in subsection (b-5) or (b-15), as applicable and as such |
standards may have been modified under this subsection (f), |
taking into account the unique circumstances of the utility's |
service territory. For those plans commencing on January 1, |
2018, the Commission shall seek public comment on the |
utility's plan and shall issue an order approving or |
disapproving each plan no later than 105 days after June 1, |
2017 (the effective date of Public Act 99-906). For those |
plans commencing after December 31, 2021, the Commission shall |
seek public comment on the utility's plan and shall issue an |
order approving or disapproving each plan within 6 months |
after its submission. If the Commission disapproves a plan, |
the Commission shall, within 30 days, describe in detail the |
reasons for the disapproval and describe a path by which the |
utility may file a revised draft of the plan to address the |
Commission's concerns satisfactorily. If the utility does not |
refile with the Commission within 60 days, the utility shall |
be subject to penalties at a rate of $100,000 per day until the |
|
plan is filed. This process shall continue, and penalties |
shall accrue, until the utility has successfully filed a |
portfolio of energy efficiency and demand-response measures. |
Penalties shall be deposited into the Energy Efficiency Trust |
Fund. |
(g) In submitting proposed plans and funding levels under |
subsection (f) of this Section to meet the savings goals |
identified in subsection (b-5) or (b-15) of this Section, as |
applicable, the utility shall: |
(1) Demonstrate that its proposed energy efficiency |
measures will achieve the applicable requirements that are |
identified in subsection (b-5) or (b-15) of this Section, |
as modified by subsection (f) of this Section. |
(2) (Blank). |
(2.5) Demonstrate consideration of program options for |
(A) advancing new building codes, appliance standards, and |
municipal regulations governing existing and new building |
efficiency improvements and (B) supporting efforts to |
improve compliance with new building codes, appliance |
standards and municipal regulations, as potentially |
cost-effective means of acquiring energy savings to count |
toward savings goals. |
(3) Demonstrate that its overall portfolio of |
measures, not including low-income programs described in |
subsection (c) of this Section, is cost-effective using |
the total resource cost test or complies with paragraphs |
|
(1) through (3) of subsection (f) of this Section and |
represents a diverse cross-section of opportunities for |
customers of all rate classes, other than those customers |
described in subsection (l) of this Section, to |
participate in the programs. Individual measures need not |
be cost effective. |
(3.5) Demonstrate that the utility's plan integrates |
the delivery of energy efficiency programs with natural |
gas efficiency programs, programs promoting distributed |
solar, programs promoting demand response and other |
efforts to address bill payment issues, including, but not |
limited to, LIHEAP and the Percentage of Income Payment |
Plan, to the extent such integration is practical and has |
the potential to enhance customer engagement, minimize |
market confusion, or reduce administrative costs. |
(4) Present a third-party energy efficiency |
implementation program subject to the following |
requirements: |
(A) beginning with the year commencing January 1, |
2019, electric utilities that serve more than |
3,000,000 retail customers in the State shall fund |
third-party energy efficiency programs in an amount |
that is no less than $25,000,000 per year, and |
electric utilities that serve less than 3,000,000 |
retail customers but more than 500,000 retail |
customers in the State shall fund third-party energy |
|
efficiency programs in an amount that is no less than |
$8,350,000 per year; |
(B) during 2018, the utility shall conduct a |
solicitation process for purposes of requesting |
proposals from third-party vendors for those |
third-party energy efficiency programs to be offered |
during one or more of the years commencing January 1, |
2019, January 1, 2020, and January 1, 2021; for those |
multi-year plans commencing on January 1, 2022 and |
January 1, 2026, the utility shall conduct a |
solicitation process during 2021 and 2025, |
respectively, for purposes of requesting proposals |
from third-party vendors for those third-party energy |
efficiency programs to be offered during one or more |
years of the respective multi-year plan period; for |
each solicitation process, the utility shall identify |
the sector, technology, or geographical area for which |
it is seeking requests for proposals; the solicitation |
process must be either for programs that fill gaps in |
the utility's program portfolio and for programs that |
target low-income customers, business sectors, |
building types, geographies, or other specific parts |
of its customer base with initiatives that would be |
more effective at reaching these customer segments |
than the utilities' programs filed in its energy |
efficiency plans; |
|
(C) the utility shall propose the bidder |
qualifications, performance measurement process, and |
contract structure, which must include a performance |
payment mechanism and general terms and conditions; |
the proposed qualifications, process, and structure |
shall be subject to Commission approval; and |
(D) the utility shall retain an independent third |
party to score the proposals received through the |
solicitation process described in this paragraph (4), |
rank them according to their cost per lifetime |
kilowatt-hours saved, and assemble the portfolio of |
third-party programs. |
The electric utility shall recover all costs |
associated with Commission-approved, third-party |
administered programs regardless of the success of those |
programs. |
(4.5) Implement cost-effective demand-response |
measures to reduce peak demand by 0.1% over the prior year |
for eligible retail customers, as defined in Section |
16-111.5 of this Act, and for customers that elect hourly |
service from the utility pursuant to Section 16-107 of |
this Act, provided those customers have not been declared |
competitive. This requirement continues until December 31, |
2026. |
(5) Include a proposed or revised cost-recovery tariff |
mechanism, as provided for under subsection (d) of this |
|
Section, to fund the proposed energy efficiency and |
demand-response measures and to ensure the recovery of the |
prudently and reasonably incurred costs of |
Commission-approved programs. |
(6) Provide for an annual independent evaluation of |
the performance of the cost-effectiveness of the utility's |
portfolio of measures, as well as a full review of the |
multi-year plan results of the broader net program impacts |
and, to the extent practical, for adjustment of the |
measures on a going-forward basis as a result of the |
evaluations. The resources dedicated to evaluation shall |
not exceed 3% of portfolio resources in any given year. |
(7) For electric utilities that serve more than |
3,000,000 retail customers in the State: |
(A) Through December 31, 2025, provide for an |
adjustment to the return on equity component of the |
utility's weighted average cost of capital calculated |
under subsection (d) of this Section: |
(i) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is less than the applicable |
annual incremental goal, then the return on equity |
component shall be reduced by a maximum of 200 |
basis points in the event that the utility |
achieved no more than 75% of such goal. If the |
utility achieved more than 75% of the applicable |
|
annual incremental goal but less than 100% of such |
goal, then the return on equity component shall be |
reduced by 8 basis points for each percent by |
which the utility failed to achieve the goal. |
(ii) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is more than the applicable |
annual incremental goal, then the return on equity |
component shall be increased by a maximum of 200 |
basis points in the event that the utility |
achieved at least 125% of such goal. If the |
utility achieved more than 100% of the applicable |
annual incremental goal but less than 125% of such |
goal, then the return on equity component shall be |
increased by 8 basis points for each percent by |
which the utility achieved above the goal. If the |
applicable annual incremental goal was reduced |
under paragraph (1) or (2) of subsection (f) of |
this Section, then the following adjustments shall |
be made to the calculations described in this item |
(ii): |
(aa) the calculation for determining |
achievement that is at least 125% of the |
applicable annual incremental goal shall use |
the unreduced applicable annual incremental |
goal to set the value; and |
|
(bb) the calculation for determining |
achievement that is less than 125% but more |
than 100% of the applicable annual incremental |
goal shall use the reduced applicable annual |
incremental goal to set the value for 100% |
achievement of the goal and shall use the |
unreduced goal to set the value for 125% |
achievement. The 8 basis point value shall |
also be modified, as necessary, so that the |
200 basis points are evenly apportioned among |
each percentage point value between 100% and |
125% achievement. |
(B) For the period January 1, 2026 through |
December 31, 2029 and in all subsequent 4-year |
periods, provide for an adjustment to the return on |
equity component of the utility's weighted average |
cost of capital calculated under subsection (d) of |
this Section: |
(i) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is less than the applicable |
annual incremental goal, then the return on equity |
component shall be reduced by a maximum of 200 |
basis points in the event that the utility |
achieved no more than 66% of such goal. If the |
utility achieved more than 66% of the applicable |
|
annual incremental goal but less than 100% of such |
goal, then the return on equity component shall be |
reduced by 6 basis points for each percent by |
which the utility failed to achieve the goal. |
(ii) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is more than the applicable |
annual incremental goal, then the return on equity |
component shall be increased by a maximum of 200 |
basis points in the event that the utility |
achieved at least 134% of such goal. If the |
utility achieved more than 100% of the applicable |
annual incremental goal but less than 134% of such |
goal, then the return on equity component shall be |
increased by 6 basis points for each percent by |
which the utility achieved above the goal. If the |
applicable annual incremental goal was reduced |
under paragraph (3) of subsection (f) of this |
Section, then the following adjustments shall be |
made to the calculations described in this item |
(ii): |
(aa) the calculation for determining |
achievement that is at least 134% of the |
applicable annual incremental goal shall use |
the unreduced applicable annual incremental |
goal to set the value; and |
|
(bb) the calculation for determining |
achievement that is less than 134% but more |
than 100% of the applicable annual incremental |
goal shall use the reduced applicable annual |
incremental goal to set the value for 100% |
achievement of the goal and shall use the |
unreduced goal to set the value for 134% |
achievement. The 6 basis point value shall |
also be modified, as necessary, so that the |
200 basis points are evenly apportioned among |
each percentage point value between 100% and |
134% achievement. |
(C) Notwithstanding the provisions of |
subparagraphs (A) and (B) of this paragraph (7), if |
the applicable annual incremental goal for an electric |
utility is ever less than 0.6% of deemed average |
weather normalized sales of electric power and energy |
during calendar years 2014, 2015, and 2016, an |
adjustment to the return on equity component of the |
utility's weighted average cost of capital calculated |
under subsection (d) of this Section shall be made as |
follows: |
(i) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is less than would have been |
achieved had the applicable annual incremental |
|
goal been achieved, then the return on equity |
component shall be reduced by a maximum of 200 |
basis points if the utility achieved no more than |
75% of its applicable annual total savings |
requirement as defined in paragraph (7.5) of this |
subsection. If the utility achieved more than 75% |
of the applicable annual total savings requirement |
but less than 100% of such goal, then the return on |
equity component shall be reduced by 8 basis |
points for each percent by which the utility |
failed to achieve the goal. |
(ii) If the independent evaluator determines |
that the utility achieved a cumulative persisting |
annual savings that is more than would have been |
achieved had the applicable annual incremental |
goal been achieved, then the return on equity |
component shall be increased by a maximum of 200 |
basis points if the utility achieved at least 125% |
of its applicable annual total savings |
requirement. If the utility achieved more than |
100% of the applicable annual total savings |
requirement but less than 125% of such goal, then |
the return on equity component shall be increased |
by 8 basis points for each percent by which the |
utility achieved above the applicable annual total |
savings requirement. If the applicable annual |
|
incremental goal was reduced under paragraph (1) |
or (2) of subsection (f) of this Section, then the |
following adjustments shall be made to the |
calculations described in this item (ii): |
(aa) the calculation for determining |
achievement that is at least 125% of the |
applicable annual total savings requirement |
shall use the unreduced applicable annual |
incremental goal to set the value; and |
(bb) the calculation for determining |
achievement that is less than 125% but more |
than 100% of the applicable annual total |
savings requirement shall use the reduced |
applicable annual incremental goal to set the |
value for 100% achievement of the goal and |
shall use the unreduced goal to set the value |
for 125% achievement. The 8 basis point value |
shall also be modified, as necessary, so that |
the 200 basis points are evenly apportioned |
among each percentage point value between 100% |
and 125% achievement. |
(7.5) For purposes of this Section, the term |
"applicable annual incremental goal" means the difference |
between the cumulative persisting annual savings goal for |
the calendar year that is the subject of the independent |
evaluator's determination and the cumulative persisting |
|
annual savings goal for the immediately preceding calendar |
year, as such goals are defined in subsections (b-5) and |
(b-15) of this Section and as these goals may have been |
modified as provided for under subsection (b-20) and |
paragraphs (1) through (3) of subsection (f) of this |
Section. Under subsections (b), (b-5), (b-10), and (b-15) |
of this Section, a utility must first replace energy |
savings from measures that have expired before any |
progress towards achievement of its applicable annual |
incremental goal may be counted. Savings may expire |
because measures installed in previous years have reached |
the end of their lives, because measures installed in |
previous years are producing lower savings in the current |
year than in the previous year, or for other reasons |
identified by independent evaluators. Notwithstanding |
anything else set forth in this Section, the difference |
between the actual annual incremental savings achieved in |
any given year, including the replacement of energy |
savings that have expired, and the applicable annual |
incremental goal shall not affect adjustments to the |
return on equity for subsequent calendar years under this |
subsection (g). |
In this Section, "applicable annual total savings |
requirement" means the total amount of new annual savings |
that the utility must achieve in any given year to achieve |
the applicable annual incremental goal. This is equal to |
|
the applicable annual incremental goal plus the total new |
annual savings that are required to replace savings that |
expired in or at the end of the previous year. |
(8) For electric utilities that serve less than |
3,000,000 retail customers but more than 500,000 retail |
customers in the State: |
(A) Through December 31, 2025, the applicable |
annual incremental goal shall be compared to the |
annual incremental savings as determined by the |
independent evaluator. |
(i) The return on equity component shall be |
reduced by 8 basis points for each percent by |
which the utility did not achieve 84.4% of the |
applicable annual incremental goal. |
(ii) The return on equity component shall be |
increased by 8 basis points for each percent by |
which the utility exceeded 100% of the applicable |
annual incremental goal. |
(iii) The return on equity component shall not |
be increased or decreased if the annual |
incremental savings as determined by the |
independent evaluator is greater than 84.4% of the |
applicable annual incremental goal and less than |
100% of the applicable annual incremental goal. |
(iv) The return on equity component shall not |
be increased or decreased by an amount greater |
|
than 200 basis points pursuant to this |
subparagraph (A). |
(B) For the period of January 1, 2026 through |
December 31, 2029 and in all subsequent 4-year |
periods, the applicable annual incremental goal shall |
be compared to the annual incremental savings as |
determined by the independent evaluator. |
(i) The return on equity component shall be |
reduced by 6 basis points for each percent by |
which the utility did not achieve 100% of the |
applicable annual incremental goal. |
(ii) The return on equity component shall be |
increased by 6 basis points for each percent by |
which the utility exceeded 100% of the applicable |
annual incremental goal. |
(iii) The return on equity component shall not |
be increased or decreased by an amount greater |
than 200 basis points pursuant to this |
subparagraph (B). |
(C) Notwithstanding provisions in subparagraphs |
(A) and (B) of paragraph (7) of this subsection, if the |
applicable annual incremental goal for an electric |
utility is ever less than 0.6% of deemed average |
weather normalized sales of electric power and energy |
during calendar years 2014, 2015 and 2016, an |
adjustment to the return on equity component of the |
|
utility's weighted average cost of capital calculated |
under subsection (d) of this Section shall be made as |
follows: |
(i) The return on equity component shall be |
reduced by 8 basis points for each percent by |
which the utility did not achieve 100% of the |
applicable annual total savings requirement. |
(ii) The return on equity component shall be |
increased by 8 basis points for each percent by |
which the utility exceeded 100% of the applicable |
annual total savings requirement. |
(iii) The return on equity component shall not |
be increased or decreased by an amount greater |
than 200 basis points pursuant to this |
subparagraph (C). |
(D) If the applicable annual incremental goal was |
reduced under paragraph (1), (2), (3), or (4) of |
subsection (f) of this Section, then the following |
adjustments shall be made to the calculations |
described in subparagraphs (A), (B), and (C) of this |
paragraph (8): |
(i) The calculation for determining |
achievement that is at least 125% or 134%, as |
applicable, of the applicable annual incremental |
goal or the applicable annual total savings |
requirement, as applicable, shall use the |
|
unreduced applicable annual incremental goal to |
set the value. |
(ii) For the period through December 31, 2025, |
the calculation for determining achievement that |
is less than 125% but more than 100% of the |
applicable annual incremental goal or the |
applicable annual total savings requirement, as |
applicable, shall use the reduced applicable |
annual incremental goal to set the value for 100% |
achievement of the goal and shall use the |
unreduced goal to set the value for 125% |
achievement. The 8 basis point value shall also be |
modified, as necessary, so that the 200 basis |
points are evenly apportioned among each |
percentage point value between 100% and 125% |
achievement. |
(iii) For the period of January 1, 2026 |
through December 31, 2029 and all subsequent |
4-year periods, the calculation for determining |
achievement that is less than 125% or 134%, as |
applicable, but more than 100% of the applicable |
annual incremental goal or the applicable annual |
total savings requirement, as applicable, shall |
use the reduced applicable annual incremental goal |
to set the value for 100% achievement of the goal |
and shall use the unreduced goal to set the value |
|
for 125% achievement. The 6 basis-point value or 8 |
basis-point value, as applicable, shall also be |
modified, as necessary, so that the 200 basis |
points are evenly apportioned among each |
percentage point value between 100% and 125% or |
between 100% and 134% achievement, as applicable. |
(9) The utility shall submit the energy savings data |
to the independent evaluator no later than 30 days after |
the close of the plan year. The independent evaluator |
shall determine the cumulative persisting annual savings |
for a given plan year, as well as an estimate of job |
impacts and other macroeconomic impacts of the efficiency |
programs for that year, no later than 120 days after the |
close of the plan year. The utility shall submit an |
informational filing to the Commission no later than 160 |
days after the close of the plan year that attaches the |
independent evaluator's final report identifying the |
cumulative persisting annual savings for the year and |
calculates, under paragraph (7) or (8) of this subsection |
(g), as applicable, any resulting change to the utility's |
return on equity component of the weighted average cost of |
capital applicable to the next plan year beginning with |
the January monthly billing period and extending through |
the December monthly billing period. However, if the |
utility recovers the costs incurred under this Section |
under paragraphs (2) and (3) of subsection (d) of this |
|
Section, then the utility shall not be required to submit |
such informational filing, and shall instead submit the |
information that would otherwise be included in the |
informational filing as part of its filing under paragraph |
(3) of such subsection (d) that is due on or before June 1 |
of each year. |
For those utilities that must submit the informational |
filing, the Commission may, on its own motion or by |
petition, initiate an investigation of such filing, |
provided, however, that the utility's proposed return on |
equity calculation shall be deemed the final, approved |
calculation on December 15 of the year in which it is filed |
unless the Commission enters an order on or before |
December 15, after notice and hearing, that modifies such |
calculation consistent with this Section. |
The adjustments to the return on equity component |
described in paragraphs (7) and (8) of this subsection (g) |
shall be applied as described in such paragraphs through a |
separate tariff mechanism, which shall be filed by the |
utility under subsections (f) and (g) of this Section. |
(9.5) The utility must demonstrate how it will ensure |
that program implementation contractors and energy |
efficiency installation vendors will promote workforce |
equity and quality jobs. |
(9.6) Utilities shall collect data necessary to ensure |
compliance with paragraph (9.5) no less than quarterly and |
|
shall communicate progress toward compliance with |
paragraph (9.5) to program implementation contractors and |
energy efficiency installation vendors no less than |
quarterly. Utilities shall work with relevant vendors, |
providing education, training, and other resources needed |
to ensure compliance and, where necessary, adjusting or |
terminating work with vendors that cannot assist with |
compliance. |
(10) Utilities required to implement efficiency |
programs under subsections (b-5) and (b-10) shall report |
annually to the Illinois Commerce Commission and the |
General Assembly on how hiring, contracting, job training, |
and other practices related to its energy efficiency |
programs enhance the diversity of vendors working on such |
programs. These reports must include data on vendor and |
employee diversity, including data on the implementation |
of paragraphs (9.5) and (9.6). If the utility is not |
meeting the requirements of paragraphs (9.5) and (9.6), |
the utility shall submit a plan to adjust their activities |
so that they meet the requirements of paragraphs (9.5) and |
(9.6) within the following year. |
(h) No more than 4% of energy efficiency and |
demand-response program revenue may be allocated for research, |
development, or pilot deployment of new equipment or measures. |
Electric utilities shall work with interested stakeholders to |
formulate a plan for how these funds should be spent, |
|
incorporate statewide approaches for these allocations, and |
file a 4-year plan that demonstrates that collaboration. If a |
utility files a request for modified annual energy savings |
goals with the Commission, then a utility shall forgo spending |
portfolio dollars on research and development proposals. |
(i) When practicable, electric utilities shall incorporate |
advanced metering infrastructure data into the planning, |
implementation, and evaluation of energy efficiency measures |
and programs, subject to the data privacy and confidentiality |
protections of applicable law. |
(j) The independent evaluator shall follow the guidelines |
and use the savings set forth in Commission-approved energy |
efficiency policy manuals and technical reference manuals, as |
each may be updated from time to time. Until such time as |
measure life values for energy efficiency measures implemented |
for low-income households under subsection (c) of this Section |
are incorporated into such Commission-approved manuals, the |
low-income measures shall have the same measure life values |
that are established for same measures implemented in |
households that are not low-income households. |
(k) Notwithstanding any provision of law to the contrary, |
an electric utility subject to the requirements of this |
Section may file a tariff cancelling an automatic adjustment |
clause tariff in effect under this Section or Section 8-103, |
which shall take effect no later than one business day after |
the date such tariff is filed. Thereafter, the utility shall |
|
be authorized to defer and recover its expenditures incurred |
under this Section through a new tariff authorized under |
subsection (d) of this Section or in the utility's next rate |
case under Article IX or Section 16-108.5 of this Act, with |
interest at an annual rate equal to the utility's weighted |
average cost of capital as approved by the Commission in such |
case. If the utility elects to file a new tariff under |
subsection (d) of this Section, the utility may file the |
tariff within 10 days after June 1, 2017 (the effective date of |
Public Act 99-906), and the cost inputs to such tariff shall be |
based on the projected costs to be incurred by the utility |
during the calendar year in which the new tariff is filed and |
that were not recovered under the tariff that was cancelled as |
provided for in this subsection. Such costs shall include |
those incurred or to be incurred by the utility under its |
multi-year plan approved under subsections (f) and (g) of this |
Section, including, but not limited to, projected capital |
investment costs and projected regulatory asset balances with |
correspondingly updated depreciation and amortization reserves |
and expense. The Commission shall, after notice and hearing, |
approve, or approve with modification, such tariff and cost |
inputs no later than 75 days after the utility filed the |
tariff, provided that such approval, or approval with |
modification, shall be consistent with the provisions of this |
Section to the extent they do not conflict with this |
subsection (k). The tariff approved by the Commission shall |
|
take effect no later than 5 days after the Commission enters |
its order approving the tariff. |
No later than 60 days after the effective date of the |
tariff cancelling the utility's automatic adjustment clause |
tariff, the utility shall file a reconciliation that |
reconciles the moneys collected under its automatic adjustment |
clause tariff with the costs incurred during the period |
beginning June 1, 2016 and ending on the date that the electric |
utility's automatic adjustment clause tariff was cancelled. In |
the event the reconciliation reflects an under-collection, the |
utility shall recover the costs as specified in this |
subsection (k). If the reconciliation reflects an |
over-collection, the utility shall apply the amount of such |
over-collection as a one-time credit to retail customers' |
bills. |
(l) For the calendar years covered by a multi-year plan |
commencing after December 31, 2017, subsections (a) through |
(j) of this Section do not apply to eligible large private |
energy customers that have chosen to opt out of multi-year |
plans consistent with this subsection (1). |
(1) For purposes of this subsection (l), "eligible |
large private energy customer" means any retail customers, |
except for federal, State, municipal, and other public |
customers, of an electric utility that serves more than |
3,000,000 retail customers, except for federal, State, |
municipal and other public customers, in the State and |
|
whose total highest 30 minute demand was more than 10,000 |
kilowatts, or any retail customers of an electric utility |
that serves less than 3,000,000 retail customers but more |
than 500,000 retail customers in the State and whose total |
highest 15 minute demand was more than 10,000 kilowatts. |
For purposes of this subsection (l), "retail customer" has |
the meaning set forth in Section 16-102 of this Act. |
However, for a business entity with multiple sites located |
in the State, where at least one of those sites qualifies |
as an eligible large private energy customer, then any of |
that business entity's sites, properly identified on a |
form for notice, shall be considered eligible large |
private energy customers for the purposes of this |
subsection (l). A determination of whether this subsection |
is applicable to a customer shall be made for each |
multi-year plan beginning after December 31, 2017. The |
criteria for determining whether this subsection (l) is |
applicable to a retail customer shall be based on the 12 |
consecutive billing periods prior to the start of the |
first year of each such multi-year plan. |
(2) Within 45 days after September 15, 2021 (the |
effective date of Public Act 102-662), the Commission |
shall prescribe the form for notice required for opting |
out of energy efficiency programs. The notice must be |
submitted to the retail electric utility 12 months before |
the next energy efficiency planning cycle. However, within |
|
120 days after the Commission's initial issuance of the |
form for notice, eligible large private energy customers |
may submit a form for notice to an electric utility. The |
form for notice for opting out of energy efficiency |
programs shall include all of the following: |
(A) a statement indicating that the customer has |
elected to opt out; |
(B) the account numbers for the customer accounts |
to which the opt out shall apply; |
(C) the mailing address associated with the |
customer accounts identified under subparagraph (B); |
(D) an American Society of Heating, Refrigerating, |
and Air-Conditioning Engineers (ASHRAE) level 2 or |
higher audit report conducted by an independent |
third-party expert identifying cost-effective energy |
efficiency project opportunities that could be |
invested in over the next 10 years. A retail customer |
with specialized processes may utilize a self-audit |
process in lieu of the ASHRAE audit; |
(E) a description of the customer's plans to |
reallocate the funds toward internal energy efficiency |
efforts identified in the subparagraph (D) report, |
including, but not limited to: (i) strategic energy |
management or other programs, including descriptions |
of targeted buildings, equipment and operations; (ii) |
eligible energy efficiency measures; and (iii) |
|
expected energy savings, itemized by technology. If |
the subparagraph (D) audit report identifies that the |
customer currently utilizes the best available energy |
efficient technology, equipment, programs, and |
operations, the customer may provide a statement that |
more efficient technology, equipment, programs, and |
operations are not reasonably available as a means of |
satisfying this subparagraph (E); and |
(F) the effective date of the opt out, which will |
be the next January 1 following notice of the opt out. |
(3) Upon receipt of a properly and timely noticed |
request for opt out submitted by an eligible large private |
energy customer, the retail electric utility shall grant |
the request, file the request with the Commission and, |
beginning January 1 of the following year, the opted out |
customer shall no longer be assessed the costs of the plan |
and shall be prohibited from participating in that 4-year |
plan cycle to give the retail utility the certainty to |
design program plan proposals. |
(4) Upon a customer's election to opt out under |
paragraphs (1) and (2) of this subsection (l) and |
commencing on the effective date of said opt out, the |
account properly identified in the customer's notice under |
paragraph (2) shall not be subject to any cost recovery |
and shall not be eligible to participate in, or directly |
benefit from, compliance with energy efficiency cumulative |
|
persisting savings requirements under subsections (a) |
through (j). |
(5) A utility's cumulative persisting annual savings |
targets will exclude any opted out load. |
(6) The request to opt out is only valid for the |
requested plan cycle. An eligible large private energy |
customer must also request to opt out for future energy |
plan cycles, otherwise the customer will be included in |
the future energy plan cycle. |
(m) Notwithstanding the requirements of this Section, as |
part of a proceeding to approve a multi-year plan under |
subsections (f) and (g) of this Section if the multi-year plan |
has been designed to maximize savings, but does not meet the |
cost cap limitations of this Section, the Commission shall |
reduce the amount of energy efficiency measures implemented |
for any single year, and whose costs are recovered under |
subsection (d) of this Section, by an amount necessary to |
limit the estimated average net increase due to the cost of the |
measures to no more than |
(1) 3.5% for each of the 4 years beginning January 1, |
2018, |
(2) (blank), |
(3) 4% for each of the 4 years beginning January 1, |
2022, |
(4) 4.25% for the 4 years beginning January 1, 2026, |
and |
|
(5) 4.25% plus an increase sufficient to account for |
the rate of inflation between January 1, 2026 and January |
1 of the first year of each subsequent 4-year plan cycle, |
of the average amount paid per kilowatthour by residential |
eligible retail customers during calendar year 2015. An |
electric utility may plan to spend up to 10% more in any year |
during an applicable multi-year plan period to |
cost-effectively achieve additional savings so long as the |
average over the applicable multi-year plan period does not |
exceed the percentages defined in items (1) through (5). To |
determine the total amount that may be spent by an electric |
utility in any single year, the applicable percentage of the |
average amount paid per kilowatthour shall be multiplied by |
the total amount of energy delivered by such electric utility |
in the calendar year 2015, adjusted to reflect the proportion |
of the utility's load attributable to customers that have |
opted out of subsections (a) through (j) of this Section under |
subsection (l) of this Section. For purposes of this |
subsection (m), the amount paid per kilowatthour includes, |
without limitation, estimated amounts paid for supply, |
transmission, distribution, surcharges, and add-on taxes. For |
purposes of this Section, "eligible retail customers" shall |
have the meaning set forth in Section 16-111.5 of this Act. |
Once the Commission has approved a plan under subsections (f) |
and (g) of this Section, no subsequent rate impact |
determinations shall be made. |
|
(n) A utility shall take advantage of the efficiencies |
available through existing Illinois Home Weatherization |
Assistance Program infrastructure and services, such as |
enrollment, marketing, quality assurance and implementation, |
which can reduce the need for similar services at a lower cost |
than utility-only programs, subject to capacity constraints at |
community action agencies, for both single-family and |
multifamily weatherization services, to the extent Illinois |
Home Weatherization Assistance Program community action |
agencies provide multifamily services. A utility's plan shall |
demonstrate that in formulating annual weatherization budgets, |
it has sought input and coordination with community action |
agencies regarding agencies' capacity to expand and maximize |
Illinois Home Weatherization Assistance Program delivery using |
the ratepayer dollars collected under this Section. |
(Source: P.A. 102-662, eff. 9-15-21; 103-154, eff. 6-30-23.) |
(220 ILCS 5/8-104) |
Sec. 8-104. Natural gas energy efficiency programs. |
(a) It is the policy of the State that natural gas |
utilities and the Department of Commerce and Economic |
Opportunity are required to use cost-effective energy |
efficiency to reduce direct and indirect costs to consumers. |
It serves the public interest to allow natural gas utilities |
to recover costs for reasonably and prudently incurred |
expenses for cost-effective energy efficiency measures. |
|
(b) For purposes of this Section, "energy efficiency" |
means measures that reduce the amount of energy required to |
achieve a given end use. "Energy efficiency" also includes |
measures that reduce the total Btus of electricity and natural |
gas needed to meet the end use or uses. "Cost-effective" means |
that the measures satisfy the total resource cost test which, |
for purposes of this Section, means a standard that is met if, |
for an investment in energy efficiency, the benefit-cost ratio |
is greater than one. The benefit-cost ratio is the ratio of the |
net present value of the total benefits of the measures to the |
net present value of the total costs as calculated over the |
lifetime of the measures. The total resource cost test |
compares the sum of avoided natural gas utility costs, |
representing the benefits that accrue to the system and the |
participant in the delivery of those efficiency measures, as |
well as other quantifiable societal benefits, including |
avoided electric utility costs, to the sum of all incremental |
costs of end use measures (including both utility and |
participant contributions), plus costs to administer, deliver, |
and evaluate each demand-side measure, to quantify the net |
savings obtained by substituting demand-side measures for |
supply resources. In calculating avoided costs, reasonable |
estimates shall be included for financial costs likely to be |
imposed by future regulation of emissions of greenhouse gases. |
The low-income programs described in item (4) of subsection |
(f) of this Section shall not be required to meet the total |
|
resource cost test. |
(c) Natural gas utilities shall implement cost-effective |
energy efficiency measures to meet at least the following |
natural gas savings requirements, which shall be based upon |
the total amount of gas delivered to retail customers, other |
than the customers described in subsection (m) of this |
Section, during calendar year 2009 multiplied by the |
applicable percentage. Natural gas utilities may comply with |
this Section by meeting the annual incremental savings goal in |
the applicable year or by showing that total cumulative annual |
savings within a multi-year planning period associated with |
measures implemented after May 31, 2011 were equal to the sum |
of each annual incremental savings requirement from the first |
day of the multi-year planning period through the last day of |
the multi-year planning period: |
(1) 0.2% by May 31, 2012; |
(2) an additional 0.4% by May 31, 2013, increasing |
total savings to .6%; |
(3) an additional 0.6% by May 31, 2014, increasing |
total savings to 1.2%; |
(4) an additional 0.8% by May 31, 2015, increasing |
total savings to 2.0%; |
(5) an additional 1% by May 31, 2016, increasing total |
savings to 3.0%; |
(6) an additional 1.2% by May 31, 2017, increasing |
total savings to 4.2%; |
|
(7) an additional 1.4% in the year commencing January |
1, 2018; |
(8) an additional 1.5% in the year commencing January |
1, 2019; and |
(9) an additional 1.5% in each 12-month period |
thereafter. |
(d) Notwithstanding the requirements of subsection (c) of |
this Section, a natural gas utility shall limit the amount of |
energy efficiency implemented in any multi-year reporting |
period established by subsection (f) of Section 8-104 of this |
Act, by an amount necessary to limit the estimated average |
increase in the amounts paid by retail customers in connection |
with natural gas service to no more than 2% in the applicable |
multi-year reporting period. The energy savings requirements |
in subsection (c) of this Section may be reduced by the |
Commission for the subject plan, if the utility demonstrates |
by substantial evidence that it is highly unlikely that the |
requirements could be achieved without exceeding the |
applicable spending limits in any multi-year reporting period. |
No later than September 1, 2013, the Commission shall review |
the limitation on the amount of energy efficiency measures |
implemented pursuant to this Section and report to the General |
Assembly, in the report required by subsection (k) of this |
Section, its findings as to whether that limitation unduly |
constrains the procurement of energy efficiency measures. |
(e) The provisions of this subsection (e) apply to those |
|
multi-year plans that commence prior to January 1, 2018. The |
utility shall utilize 75% of the available funding associated |
with energy efficiency programs approved by the Commission, |
and may outsource various aspects of program development and |
implementation. The remaining 25% of available funding shall |
be used by the Department of Commerce and Economic Opportunity |
to implement energy efficiency measures that achieve no less |
than 20% of the requirements of subsection (c) of this |
Section. Such measures shall be designed in conjunction with |
the utility and approved by the Commission. The Department may |
outsource development and implementation of energy efficiency |
measures. A minimum of 10% of the entire portfolio of |
cost-effective energy efficiency measures shall be procured |
from local government, municipal corporations, school |
districts, public institutions of higher education, and |
community college districts. Five percent of the entire |
portfolio of cost-effective energy efficiency measures may be |
granted to local government and municipal corporations for |
market transformation initiatives. The Department shall |
coordinate the implementation of these measures and shall |
integrate delivery of natural gas efficiency programs with |
electric efficiency programs delivered pursuant to Section |
8-103 of this Act, unless the Department can show that |
integration is not feasible. |
The apportionment of the dollars to cover the costs to |
implement the Department's share of the portfolio of energy |
|
efficiency measures shall be made to the Department once the |
Department has executed rebate agreements, grants, or |
contracts for energy efficiency measures and provided |
supporting documentation for those rebate agreements, grants, |
and contracts to the utility. The Department is authorized to |
adopt any rules necessary and prescribe procedures in order to |
ensure compliance by applicants in carrying out the purposes |
of rebate agreements for energy efficiency measures |
implemented by the Department made under this Section. |
The details of the measures implemented by the Department |
shall be submitted by the Department to the Commission in |
connection with the utility's filing regarding the energy |
efficiency measures that the utility implements. |
The portfolio of measures, administered by both the |
utilities and the Department, shall, in combination, be |
designed to achieve the annual energy savings requirements set |
forth in subsection (c) of this Section, as modified by |
subsection (d) of this Section. |
The utility and the Department shall agree upon a |
reasonable portfolio of measures and determine the measurable |
corresponding percentage of the savings goals associated with |
measures implemented by the Department. |
No utility shall be assessed a penalty under subsection |
(f) of this Section for failure to make a timely filing if that |
failure is the result of a lack of agreement with the |
Department with respect to the allocation of responsibilities |
|
or related costs or target assignments. In that case, the |
Department and the utility shall file their respective plans |
with the Commission and the Commission shall determine an |
appropriate division of measures and programs that meets the |
requirements of this Section. |
(e-5) The provisions of this subsection (e-5) shall be |
applicable to those multi-year plans that commence after |
December 31, 2017. Natural gas utilities shall be responsible |
for overseeing the design, development, and filing of their |
efficiency plans with the Commission and may outsource |
development and implementation of energy efficiency measures. |
A minimum of 10% of the entire portfolio of cost-effective |
energy efficiency measures shall be procured from local |
government, municipal corporations, school districts, public |
institutions of higher education, and community college |
districts. Five percent of the entire portfolio of |
cost-effective energy efficiency measures may be granted to |
local government and municipal corporations for market |
transformation initiatives. |
The utilities shall also present a portfolio of energy |
efficiency measures proportionate to the share of total annual |
utility revenues in Illinois from households at or below 150% |
of the poverty level. Such programs shall be targeted to |
households with incomes at or below 80% of area median income. |
(e-10) A utility providing approved energy efficiency |
measures in this State shall be permitted to recover costs of |
|
those measures through an automatic adjustment clause tariff |
filed with and approved by the Commission. The tariff shall be |
established outside the context of a general rate case and |
shall be applicable to the utility's customers other than the |
customers described in subsection (m) of this Section. Each |
year the Commission shall initiate a review to reconcile any |
amounts collected with the actual costs and to determine the |
required adjustment to the annual tariff factor to match |
annual expenditures. |
(e-15) For those multi-year plans that commence prior to |
January 1, 2018, each utility shall include, in its recovery |
of costs, the costs estimated for both the utility's and the |
Department's implementation of energy efficiency measures. |
Costs collected by the utility for measures implemented by the |
Department shall be submitted to the Department pursuant to |
Section 605-323 of the Civil Administrative Code of Illinois, |
shall be deposited into the Energy Efficiency Portfolio |
Standards Fund, and shall be used by the Department solely for |
the purpose of implementing these measures. A utility shall |
not be required to advance any moneys to the Department but |
only to forward such funds as it has collected. The Department |
shall report to the Commission on an annual basis regarding |
the costs actually incurred by the Department in the |
implementation of the measures. Any changes to the costs of |
energy efficiency measures as a result of plan modifications |
shall be appropriately reflected in amounts recovered by the |
|
utility and turned over to the Department. |
(f) No later than October 1, 2010, each gas utility shall |
file an energy efficiency plan with the Commission to meet the |
energy efficiency standards through May 31, 2014. No later |
than October 1, 2013, each gas utility shall file an energy |
efficiency plan with the Commission to meet the energy |
efficiency standards through May 31, 2017. Beginning in 2017 |
and every 4 years thereafter, each utility shall file an |
energy efficiency plan with the Commission to meet the energy |
efficiency standards for the next applicable 4-year period |
beginning January 1 of the year following the filing. For |
those multi-year plans commencing on January 1, 2018, each |
utility shall file its proposed energy efficiency plan no |
later than 30 days after the effective date of this amendatory |
Act of the 99th General Assembly or May 1, 2017, whichever is |
later. Beginning in 2021 and every 4 years thereafter, each |
utility shall file its energy efficiency plan no later than |
March 1. If a utility does not file such a plan on or before |
the applicable filing deadline for the plan, then it shall |
face a penalty of $100,000 per day until the plan is filed. |
Each utility's plan shall set forth the utility's |
proposals to meet the utility's portion of the energy |
efficiency standards identified in subsection (c) of this |
Section, as modified by subsection (d) of this Section, taking |
into account the unique circumstances of the utility's service |
territory. For those plans commencing after December 31, 2021, |
|
the Commission shall seek public comment on the utility's plan |
and shall issue an order approving or disapproving each plan |
within 6 months after its submission. For those plans |
commencing on January 1, 2018, the Commission shall seek |
public comment on the utility's plan and shall issue an order |
approving or disapproving each plan no later than August 31, |
2017, or 105 days after the effective date of this amendatory |
Act of the 99th General Assembly, whichever is later. If the |
Commission disapproves a plan, the Commission shall, within 30 |
days, describe in detail the reasons for the disapproval and |
describe a path by which the utility may file a revised draft |
of the plan to address the Commission's concerns |
satisfactorily. If the utility does not refile with the |
Commission within 60 days after the disapproval, the utility |
shall be subject to penalties at a rate of $100,000 per day |
until the plan is filed. This process shall continue, and |
penalties shall accrue, until the utility has successfully |
filed a portfolio of energy efficiency measures. Penalties |
shall be deposited into the Energy Efficiency Trust Fund and |
the cost of any such penalties may not be recovered from |
ratepayers. In submitting proposed energy efficiency plans and |
funding levels to meet the savings goals adopted by this Act |
the utility shall: |
(1) Demonstrate that its proposed energy efficiency |
measures will achieve the requirements that are identified |
in subsection (c) of this Section, as modified by |
|
subsection (d) of this Section. |
(2) Present specific proposals to implement new |
building and appliance standards that have been placed |
into effect. |
(3) Present estimates of the total amount paid for gas |
service expressed on a per therm basis associated with the |
proposed portfolio of measures designed to meet the |
requirements that are identified in subsection (c) of this |
Section, as modified by subsection (d) of this Section. |
(4) For those multi-year plans that commence prior to |
January 1, 2018, coordinate with the Department to present |
a portfolio of energy efficiency measures proportionate to |
the share of total annual utility revenues in Illinois |
from households at or below 150% of the poverty level. |
Such programs shall be targeted to households with incomes |
at or below 80% of area median income. |
(5) Demonstrate that its overall portfolio of energy |
efficiency measures, not including low-income programs |
described in item (4) of this subsection (f) and |
subsection (e-5) of this Section, are cost-effective using |
the total resource cost test and represent a diverse cross |
section of opportunities for customers of all rate classes |
to participate in the programs. |
(6) Demonstrate that a gas utility affiliated with an |
electric utility that is required to comply with Section |
8-103 or 8-103B of this Act has integrated gas and |
|
electric efficiency measures into a single program that |
reduces program or participant costs and appropriately |
allocates costs to gas and electric ratepayers. For those |
multi-year plans that commence prior to January 1, 2018, |
the Department shall integrate all gas and electric |
programs it delivers in any such utilities' service |
territories, unless the Department can show that |
integration is not feasible or appropriate. |
(7) Include a proposed cost recovery tariff mechanism |
to fund the proposed energy efficiency measures and to |
ensure the recovery of the prudently and reasonably |
incurred costs of Commission-approved programs. |
(8) Provide for quarterly status reports tracking |
implementation of and expenditures for the utility's |
portfolio of measures and, if applicable, the Department's |
portfolio of measures, an annual independent review, and a |
full independent evaluation of the multi-year results of |
the performance and the cost-effectiveness of the |
utility's and, if applicable, Department's portfolios of |
measures and broader net program impacts and, to the |
extent practical, for adjustment of the measures on a |
going forward basis as a result of the evaluations. The |
resources dedicated to evaluation shall not exceed 3% of |
portfolio resources in any given multi-year period. |
(g) No more than 3% of expenditures on energy efficiency |
measures may be allocated for demonstration of breakthrough |
|
equipment and devices. |
(h) Illinois natural gas utilities that are affiliated by |
virtue of a common parent company may, at the utilities' |
request, be considered a single natural gas utility for |
purposes of complying with this Section. |
(i) If, after 3 years, a gas utility fails to meet the |
efficiency standard specified in subsection (c) of this |
Section as modified by subsection (d), then it shall make a |
contribution to the Low-Income Home Energy Assistance Program. |
The total liability for failure to meet the goal shall be |
assessed as follows: |
(1) a large gas utility shall pay $600,000; |
(2) a medium gas utility shall pay $400,000; and |
(3) a small gas utility shall pay $200,000. |
For purposes of this Section, (i) a "large gas utility" is |
a gas utility that on December 31, 2008, served more than |
1,500,000 gas customers in Illinois; (ii) a "medium gas |
utility" is a gas utility that on December 31, 2008, served |
fewer than 1,500,000, but more than 500,000 gas customers in |
Illinois; and (iii) a "small gas utility" is a gas utility that |
on December 31, 2008, served fewer than 500,000 and more than |
100,000 gas customers in Illinois. The costs of this |
contribution may not be recovered from ratepayers. |
If a gas utility fails to meet the efficiency standard |
specified in subsection (c) of this Section, as modified by |
subsection (d) of this Section, in any 2 consecutive |
|
multi-year planning periods, then the responsibility for |
implementing the utility's energy efficiency measures shall be |
transferred to an independent program administrator selected |
by the Commission. Reasonable and prudent costs incurred by |
the independent program administrator to meet the efficiency |
standard specified in subsection (c) of this Section, as |
modified by subsection (d) of this Section, may be recovered |
from the customers of the affected gas utilities, other than |
customers described in subsection (m) of this Section. The |
utility shall provide the independent program administrator |
with all information and assistance necessary to perform the |
program administrator's duties including but not limited to |
customer, account, and energy usage data, and shall allow the |
program administrator to include inserts in customer bills. |
The utility may recover reasonable costs associated with any |
such assistance. |
(j) No utility shall be deemed to have failed to meet the |
energy efficiency standards to the extent any such failure is |
due to a failure of the Department. |
(k) Not later than January 1, 2012, the Commission shall |
develop and solicit public comment on a plan to foster |
statewide coordination and consistency between statutorily |
mandated natural gas and electric energy efficiency programs |
to reduce program or participant costs or to improve program |
performance. Not later than September 1, 2013, the Commission |
shall issue a report to the General Assembly containing its |
|
findings and recommendations. |
(l) This Section does not apply to a gas utility that on |
January 1, 2009, provided gas service to fewer than 100,000 |
customers in Illinois. |
(m) Subsections (a) through (k) of this Section do not |
apply to customers of a natural gas utility that have a North |
American Industry Classification System code number that is |
22111 or any such code number beginning with the digits 31, 32, |
or 33 and (i) annual usage in the aggregate of 4 million therms |
or more within the service territory of the affected gas |
utility or with aggregate usage of 8 million therms or more in |
this State and complying with the provisions of item (l) of |
this subsection (m); or (ii) using natural gas as feedstock |
and meeting the usage requirements described in item (i) of |
this subsection (m), to the extent such annual feedstock usage |
is greater than 60% of the customer's total annual usage of |
natural gas. |
(1) Customers described in this subsection (m) of this |
Section shall apply, on a form approved on or before |
October 1, 2009 by the Department, to the Department to be |
designated as a self-directing customer ("SDC") or as an |
exempt customer using natural gas as a feedstock from |
which other products are made, including, but not limited |
to, feedstock for a hydrogen plant, on or before the 1st |
day of February, 2010. Thereafter, application may be made |
not less than 6 months before the filing date of the gas |
|
utility energy efficiency plan described in subsection (f) |
of this Section; however, a new customer that commences |
taking service from a natural gas utility after February |
1, 2010 may apply to become a SDC or exempt customer up to |
30 days after beginning service. Customers described in |
this subsection (m) that have not already been approved by |
the Department may apply to be designated a self-directing |
customer or exempt customer, on a form approved by the |
Department, between September 1, 2013 and September 30, |
2013. Customer applications that are approved by the |
Department under this amendatory Act of the 98th General |
Assembly shall be considered to be a self-directing |
customer or exempt customer, as applicable, for the |
current 3-year planning period effective December 1, 2013. |
Such application shall contain the following: |
(A) the customer's certification that, at the time |
of its application, it qualifies to be a SDC or exempt |
customer described in this subsection (m) of this |
Section; |
(B) in the case of a SDC, the customer's |
certification that it has established or will |
establish by the beginning of the utility's multi-year |
planning period commencing subsequent to the |
application, and will maintain for accounting |
purposes, an energy efficiency reserve account and |
that the customer will accrue funds in said account to |
|
be held for the purpose of funding, in whole or in |
part, energy efficiency measures of the customer's |
choosing, which may include, but are not limited to, |
projects involving combined heat and power systems |
that use the same energy source both for the |
generation of electrical or mechanical power and the |
production of steam or another form of useful thermal |
energy or the use of combustible gas produced from |
biomass, or both; |
(C) in the case of a SDC, the customer's |
certification that annual funding levels for the |
energy efficiency reserve account will be equal to 2% |
of the customer's cost of natural gas, composed of the |
customer's commodity cost and the delivery service |
charges paid to the gas utility, or $150,000, |
whichever is less; |
(D) in the case of a SDC, the customer's |
certification that the required reserve account |
balance will be capped at 3 years' worth of accruals |
and that the customer may, at its option, make further |
deposits to the account to the extent such deposit |
would increase the reserve account balance above the |
designated cap level; |
(E) in the case of a SDC, the customer's |
certification that by October 1 of each year, |
beginning no sooner than October 1, 2012, the customer |
|
will report to the Department information, for the |
12-month period ending May 31 of the same year, on all |
deposits and reductions, if any, to the reserve |
account during the reporting year, and to the extent |
deposits to the reserve account in any year are in an |
amount less than $150,000, the basis for such reduced |
deposits; reserve account balances by month; a |
description of energy efficiency measures undertaken |
by the customer and paid for in whole or in part with |
funds from the reserve account; an estimate of the |
energy saved, or to be saved, by the measure; and that |
the report shall include a verification by an officer |
or plant manager of the customer or by a registered |
professional engineer or certified energy efficiency |
trade professional that the funds withdrawn from the |
reserve account were used for the energy efficiency |
measures; |
(F) in the case of an exempt customer, the |
customer's certification of the level of gas usage as |
feedstock in the customer's operation in a typical |
year and that it will provide information establishing |
this level, upon request of the Department; |
(G) in the case of either an exempt customer or a |
SDC, the customer's certification that it has provided |
the gas utility or utilities serving the customer with |
a copy of the application as filed with the |
|
Department; |
(H) in the case of either an exempt customer or a |
SDC, certification of the natural gas utility or |
utilities serving the customer in Illinois including |
the natural gas utility accounts that are the subject |
of the application; and |
(I) in the case of either an exempt customer or a |
SDC, a verification signed by a plant manager or an |
authorized corporate officer attesting to the |
truthfulness and accuracy of the information contained |
in the application. |
(2) The Department shall review the application to |
determine that it contains the information described in |
provisions (A) through (I) of item (1) of this subsection |
(m), as applicable. The review shall be completed within |
30 days after the date the application is filed with the |
Department. Absent a determination by the Department |
within the 30-day period, the applicant shall be |
considered to be a SDC or exempt customer, as applicable, |
for all subsequent multi-year planning periods, as of the |
date of filing the application described in this |
subsection (m). If the Department determines that the |
application does not contain the applicable information |
described in provisions (A) through (I) of item (1) of |
this subsection (m), it shall notify the customer, in |
writing, of its determination that the application does |
|
not contain the required information and identify the |
information that is missing, and the customer shall |
provide the missing information within 15 working days |
after the date of receipt of the Department's |
notification. |
(3) The Department shall have the right to audit the |
information provided in the customer's application and |
annual reports to ensure continued compliance with the |
requirements of this subsection. Based on the audit, if |
the Department determines the customer is no longer in |
compliance with the requirements of items (A) through (I) |
of item (1) of this subsection (m), as applicable, the |
Department shall notify the customer in writing of the |
noncompliance. The customer shall have 30 days to |
establish its compliance, and failing to do so, may have |
its status as a SDC or exempt customer revoked by the |
Department. The Department shall treat all information |
provided by any customer seeking SDC status or exemption |
from the provisions of this Section as strictly |
confidential. |
(4) Upon request, or on its own motion, the Commission |
may open an investigation, no more than once every 3 years |
and not before October 1, 2014, to evaluate the |
effectiveness of the self-directing program described in |
this subsection (m). |
Customers described in this subsection (m) that applied to |
|
the Department on January 3, 2013, were approved by the |
Department on February 13, 2013 to be a self-directing |
customer or exempt customer, and receive natural gas from a |
utility that provides gas service to at least 500,000 retail |
customers in Illinois and electric service to at least |
1,000,000 retail customers in Illinois shall be considered to |
be a self-directing customer or exempt customer, as |
applicable, for the current 3-year planning period effective |
December 1, 2013. |
(n) The applicability of this Section to customers |
described in subsection (m) of this Section is conditioned on |
the existence of the SDC program. In no event will any |
provision of this Section apply to such customers after |
January 1, 2020. |
(o) Utilities' 3-year energy efficiency plans approved by |
the Commission on or before the effective date of this |
amendatory Act of the 99th General Assembly for the period |
June 1, 2014 through May 31, 2017 shall continue to be in force |
and effect through December 31, 2017 so that the energy |
efficiency programs set forth in those plans continue to be |
offered during the period June 1, 2017 through December 31, |
2017. Each utility is authorized to increase, on a pro rata |
basis, the energy savings goals and budgets approved in its |
plan to reflect the additional 7 months of the plan's |
operation. |
(Source: P.A. 98-90, eff. 7-15-13; 98-225, eff. 8-9-13; |